Legal development

Campus to Capital | The chips need a passport

Abstract fan of glowing, translucent petals in teal, aqua and soft peach.

    Power is local. A campus wins or loses its megawatts through zoning fights, permit queues and moratoriums.

    Compute is global. Capacity can be sold to customers thousands of miles away.

    Capital spans both. A lender in Asia, a sponsor in the Middle East and a tenant in the US can share one term sheet.

    The chips are the odd one out.

    The Commerce Department’s new remote-access rule, effective November 19, looks past where advanced chips ship to who uses the compute.

    A data center anywhere may now need a license for covered chips if it gives companies headquartered or parented in China, Macau or another Country Group D:5 country more than 12 million aggregate TPP of compute, at one site or across linked sites.

    It also adds a license requirement for shipments to Indonesia, Malaysia, Singapore, Thailand and Brazil, with a reporting-based exclusion for US-headquartered customers. Our analysis: https://www.ashurstperkinscoie.com/en/insights/bis-issues-interim-final-rule-restricting-remote-access-to-advanced-us-ai-chips/

    What does that mean for the capital stack?

    1. The customer list is now collateral

    Lenders have always cared about the tenant. Now downstream users, their ultimate parents and their workloads can affect the chips’ licensing position. Know-your-customer is becoming part of the credit assessment.

    2. The paperwork is now part of the delivery schedule

    In Southeast Asia, the customer’s identity and ownership now shape the licensing path and the timetable for new compute. That doesn’t make the capacity unfinanceable. It does mean licensing conditions, delivery dates, substitute-region rights and license-denial risk belong in the documents before chips are ordered.

    A late license means late equipment, late capacity and late revenue.

    3. Residual value depends on who can legally buy

    Our first piece argued that custom silicon can thin the recovery floor because fewer buyers can redeploy it economically. Merchant GPUs can have more buyers, but only legally eligible ones count, and eligibility doesn’t stop at the rack. A change in customer, ownership or use that crosses the end-use test can require authorization for installed chips. Data centers already serving covered companies at that scale have 90 days from November 19 to get licensed.

    Whoever carries that risk should be paid for it. The documents need to answer:

    • Who monitors the customer and its ownership?
    • Who controls capacity allocation?
    • Who applies for the license?
    • Who carries the cost of delay?
    • What happens if authorization never lands?

    Ownership-change notices, eligibility covenants, information and audit rights, suspension rights and regulatory outside dates are the usual tools.

    The campus is sited for power and financed on offtake. The value of the chips inside may now depend on who is allowed to log in.

    The silicon needs a passport. Now its capacity does too.

    Want to know more? 

    Visit our Data Centers hub for more insights. 

    Data Centers – A modern digital asset class

    Read more in the series: 

    Campus to Capital | Behind the meter isn't beyond the regulator

    Campus to Capital | The campus hasn't changed. The collateral has.

    Campus to Capital | The campus is the vision. The phase is the investment.

    Authors: Jane Rueger, Partner; Michael Herrera, Partner; Camarin Madigan, Partner; Tamara McKinzie, Partner; Jamie Ng, Global Clients & Markets Partner.

    The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
    Readers should take legal advice before applying it to specific issues or transactions.

    Key Contacts