Campus to Capital | The campus is the vision. The phase is the investment.

Abstract fan of glowing, translucent petals in teal, aqua and soft peach.

    The campus is the vision. The phase is the investment. 

    Picture a data center campus where the halls are on schedule and the chips are arriving. 

    The first 100 MW has power, permits and equipment. The next 400 MW? 

    Still waiting on some combination of power, approvals, transformers, turbines or contractor capacity. 

    Behind-the-meter power may change where the infrastructure risk sits. Phasing changes when the capital is exposed to it. 

    For a financier, the question is no longer simply: 

    "Is the campus ready?" 

    It is: 

    "Which phase can actually earn revenue, and what happens to our money if the next one can't?" 

    That is changing the unit of development and, increasingly, the unit of capital. 

    A 500 MW campus may be one development vision, but it is not necessarily one financeable asset. Each phase can have its own permits, energization date, equipment allocation, customer commitment and exposure to delay. This means capital increasingly follows the phase. 

    A lender can underwrite the 100 MW that has power, permits and a customer more confidently than the 400 MW still dependent on things that haven't happened. 

    The legal structure can support it too. Where halls or phases comprise separate parcels or condominium units, they can potentially be financed, refinanced or sold on different schedules, while sharing common campus infrastructure. Commercial condominium structures are already used to support separate ownership and financing of data center components alongside shared utility infrastructure. 

    And the upfront-capital difference can be material. 

    In Texas, the new large-load interconnection rule illustrates the choice. A qualifying customer must post $50,000/MW of financial security against the requested peak demand before the ERCOT interconnection study, plus a $100,000 study fee. A 100 MW request therefore means $5 million of initial security; a 500 MW request means $25 million. 

    That makes phasing attractive. 

    But phasing cuts both ways. 

    Commit less today and you preserve capital. You may also preserve less capacity for tomorrow. 

    A successful first phase can come at the expense of later ones if grid capacity, equipment slots, contractor availability or permits become harder to secure. In the financial security example above, limiting the large load request can also mean leaving the later capacity to a future study and allocation, which could add a year or more to the timeline for future phases. Texas' rule also requires detailed disclosure of phased energization schedules, while material changes to peak demand or the ramp schedule may require a new request, meaning choices on phasing need to be made early. 

    Campus-wide development can also capture things phasing may give up: economies of scale, common infrastructure, coordinated permitting and a single mobilization of the construction supply chain. 

    The interesting question isn't whether phased development is safer. 

    It is how much risk and optionality you are moving into the later phases. 

    The campus may still be the vision, but increasingly, the phase is the investment. 

    Want to know more?  

    Visit our Data Centers hub for more insights.  

    Data Centres – A modern digital asset class.

    Read more in the series:  

    Campus to Capital | Behind the meter isn't beyond the regulator.

    Campus to Capital | The campus hasn't changed. The collateral has. 

    Authors: Jane Rueger, Partner; Michael Herrera, Partner; Camarin Madigan, Partner; Jamie Ng, Partner.

    The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
    Readers should take legal advice before applying it to specific issues or transactions.

    Key Contacts