Frequently Asked Questions Follow-Up: What Contractors Should Know as the Government Reopens
With the government shutdown officially over and government operations resuming, contractors face critical decisions about restarting work, managing compliance, and protecting their contractual rights.
Timely action can help avoid delays, preserve claims, and ensure smooth performance. As a complement to our Update published at the beginning of the shutdown, below is a set of frequently asked questions designed to provide contractors with practical guidance for navigating this transition period.
Contractors should:
Contractors should pay close attention to any contract changes during this shutdown in particular because the government reallocated funds to cover other priorities, which may have led to significant changes in both new and existing contracts. Contract changes made during the shutdown may allow the contractor to seek an equitable adjustment or file a claim under the Contract Disputes Act (CDA) to recover costs or negotiate new terms.
Contractors should also monitor FAR reform initiatives, especially the General Services Administration’s Revolutionary FAR Overhaul project and sunset clauses for outdated provisions. FAR updates effective October 2025 include streamlined procedures for commercial products and services (FAR 12.203) and revised contractor quality responsibilities (FAR 46.105). Agencies are implementing these changes as class deviations and removing outdated clauses.
Contractors should resume work in a structured and systematic way by:
Yes. Contractors may submit claims for allowable costs, such as idle labor or demobilization expenses. Contractors can potentially recover costs, under certain FAR clauses, for the following categories: standby labor, restart costs, subcontractor pass-through costs, and schedule disruption expenses. However, recovering these costs requires thorough documentation, and the review process takes time. Our prior Update provides additional details about recoverable costs and documentation (see responses 5 and 6).
Further, as we briefly discussed in our prior Update (see response 8), there are several mechanisms for recovering shutdown-related costs. If the financial impact is significant, it is typical to start with a Request for Equitable Adjustment (REA), which can allow for negotiated relief without escalating to litigation. If an REA fails, contractors may consider converting the REA into a claim under the CDA. A CDA claim triggers formal timelines and preserves a contractor’s right to appeal to a board of contract appeals or the Court of Federal Claims. Maintaining contemporaneous records—daily logs, CO communications, and subcontractor invoices—is critical to support either approach.
Importantly, under the FAR Stop-Work Order clause (FAR 52.242-15), contractors must assert any claim within 30 days after the stop-work order is canceled or expires or, at the latest, before final payment. For the Suspension of Work clause (FAR 52.242-14), which is more typically used in construction contracts, claims should be submitted as soon as practicable but no later than final payment.
Contractors should also be prepared to demonstrate that any incurred costs being claimed are allowable and related to the shutdown, as discussed in our prior Update (see response 9).
Contractors should submit any pending invoices immediately and confirm receipt. Contractors should also track payments closely and keep in mind that if delays occur, they may be entitled to interest under the Prompt Payment Act (PPA). This is treated differently depending on whether the invoice was accepted before or after the shutdown.
If the government accepted a proper invoice before the shutdown, the 30-day PPA clock starts from that acceptance date. If payment becomes overdue during the shutdown, interest accrues for every day past the due date—even while the government is closed. For example, a proper invoice accepted on September 23, 2025 (before the October 1, 2025, shutdown) would be due for payment by October 23, 2025, so interest begins accruing from October 24, 2025, until payment is made.
If your invoice was submitted before or during the shutdown but not accepted until after reopening, the clock does not start until acceptance occurs. Interest accrues only after 30 days from the acceptance date, regardless of when you originally submitted the invoice. For example, a proper invoice submitted on September 25, 2025 (before the October 1, 2025, shutdown) and accepted on November 10, 2025, would be due for payment by December 10, 2025, so interest accrues starting on December 11, 2025, if it remains unpaid.
If a contractor determines they are owed interest under the PPA, the contractor should confirm the acceptance date of the invoice and calculate the interest owed using the U.S. Department of the Treasury’s published rate. Then, the contractor should notify their CO in writing with the invoice details and interest amount. If interest is not paid within 10 days, the contractor may submit a formal written demand that the agency pay an additional penalty (capped at $5,000) due to not providing the late payment interest already owed. Contractors can also escalate through the CDA process if necessary.
By addressing transition issues proactively, contractors can minimize risk, maintain compliance, and position themselves for success as government operations return to normal.
These FAQs are intended as general guidance; contractors should evaluate contract-specific terms and consult counsel for tailored advice.
The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
Readers should take legal advice before applying it to specific issues or transactions.