Data Centres: What Has Changed in the Draft Royal Decree?
Following the ending, on 10 September 2026, of the public consultation and hearing process on the Draft Royal Decree regulating the energy and environmental sustainability, resilience and digital sovereignty requirements applicable to data centres (Draft RD), a new version of the text has been circulating in the industry (New Draft).
In our previous briefing note, we analysed the content of the version submitted to public consultation. In this note, we focus exclusively on the changes introduced by the New Draft, which has been submitted to the Council of State for its consideration.
The analysis in this note is based on a version of the Draft RD that has not been published by any official source. Its content may not correspond exactly to the text submitted to the Council of State and, in any event, the Council of Ministers may introduce substantial changes before final approval.
This note should not be relied upon as a basis for decision-making without a specific analysis of the text ultimately approved.
The public consultation and hearing process on the Draft RD ended on 10 September 2026. Following the report of the National Markets and Competition Commission (CNMC), the Government has prepared a new text (analysed here) for referral to the Council of State, which incorporates changes arising from that report and from the public consultation. Because the Draft RD is being processed under the urgency procedure, the Council of State has fifteen days to issue its opinion, which, although mandatory, is not binding. Accordingly, even if the full urgency period is used, the opinion could be issued around 18 November. This would allow the Government to approve the final text, with or without changes to the New Draft, before the general election on 29 November 2026, as it has publicly stated.
The New Draft maintains entry into force twenty days after its publication in the Official State Gazette (BOE). This date should be borne in mind, as it determines the calculation of all the transitional periods analysed below. Note also that the transitional provisions have been renumbered (former Transitional Provisions 1 to 4 become Transitional Provisions 3 to 6, and former Transitional Provision 5 has been deleted). Unless otherwise indicated, references in this note are to the numbering of the New Draft.
|
Topic |
Draft RD |
New Draft |
|---|---|---|
|
Scope threshold (Article 2) |
Access capacity ≥ 1 MW. |
Access capacity ≥ 10 MW (Article 5 on digital sovereignty applies regardless of capacity). New exclusion for State public sector data centres that qualify as critical operators. |
|
Digital sovereignty (Article 5) |
General requirements for all data centres (establishment in the EU, data retention, traceability, subcontractors). Deferred application with no deadline. |
Restriction on hosting systems in the HIGH category (categoría ALTA) under the National Security Framework (ENS), with exceptions and conditions. Obligated party: the data centre owner (titular), not the operator. Ministerial order approving the model responsible statement within six months, or direct application. |
|
PUE / WUE (Article 6 and Transitional Provision 6) |
Class «A». During the transitional period, PUE ≤ 1.15 and WUE ≤ 0.1. |
Class «A», pending a ministerial order. During the transitional period, PUE ≤ 1.25 (WUE remains at ≤ 0.1). PUE normalised by climate zone, subject to a ministerial order (Additional Provision 4). Compliance required six months after the data centre starts operating. |
|
Additionality (Article 8) |
18-month window from when the data centre starts operating: ATR contract or first consumption, if earlier. |
Window extended to 36 months before the data centre starts operating (signing of the ATR contract). Contracts with storage facilities, repowered facilities, biomass facilities at the end of their regulatory life and photovoltaic facilities without a PPA, regardless of age, are admitted. |
|
Hourly matching and surcharges for non-compliance (Articles 9 and 10) |
Surcharges of 10%, 30% and 50% depending on the percentage of hours; +10 p.p. for each consecutive month. |
Storage admitted, with monthly verification for hybrid facilities. Additional hourly matching surcharges: five bands (10%-100%) applied to the arithmetic mean of the month’s hourly percentages; +10 p.p. for each consecutive year. |
|
PPAs (Article 12) |
Minimum term of 10 years. |
Minimum term of 6 years. Annual redemption of the guarantees of origin by the generation owner before the CNMC, stating the data centre’s CUPS (the Spanish universal supply point code). |
|
New transitional regimes |
|
Transitional Provision 1: option to join the Automatic Power Reduction System (SRAP) in exchange for more flexible hourly matching requirements. Transitional Provision 2: European strategic projects aimed at digital sovereignty. Transitional Provision 7: initial period of six months from the ATR contract to meet the additionality requirement (until 31 December 2028); and Transitional Provision 8: PUE ≤ 1.25 until 31 December 2031 for data centres with an ATR contract signed before 2029. |
Background: The Draft RD applied the obligations to data centres with access capacity of 1 MW or more (and to groups of data centres located at the same site and under common ownership which, in aggregate, reached that capacity). It also defined “access capacity” as the capacity stated in the permits or, if higher, the capacity contracted under the ATR contract. Article 2.2 included network operators and the CNMC, within the scope of their respective powers. It only excluded data centres used exclusively for defence, civil protection and public safety.
The New Draft raises the access capacity threshold from 1 MW to 10 MW, above which data centres become subject to the Royal Decree. The threshold includes groups of data centres under common ownership, although the criterion for grouping has still not been specified. It also deletes the definition of “access capacity” and the reference to the CNMC in Article 2.2. As a new feature, the following are excluded: (i) facilities with ICT equipment whose main activity is not that of a data centre, in which only the capacity exclusively allocated to that activity is counted; and (ii) data centres of State public sector entities that are critical operators under Law 8/2011, or that are attached to such entities.
The threshold does not apply to the digital sovereignty obligations (Article 5). The disclosure obligations on energy efficiency and sustainability (Article 14) continue to apply to data centres with IT power capacity of 500 kW or more, unchanged from the Draft RD.
With the new threshold, many smaller edge and colocation projects would not be subject to the additional grid access requirements (efficiency, additionality and hourly matching). This responds to the market’s calls for proportionality.
Background: In the Draft RD, Article 5 imposed on all data centres within its scope a set of general requirements (establishment in the EU, retention in the EU of data, metadata and records, traceability of support operations from third countries, supervision of direct subcontractors and measures against access by third-country authorities), to be demonstrated through two responsible statements. Their application (except for certain sections) was deferred, with no deadline, until a ministerial order was approved (former Transitional Provision 5, now deleted).
The New Draft removes resilience and focuses Article 5 on digital sovereignty. The data centre owner may not host systems in the HIGH category under the ENS unless three conditions are met.
The conditions only apply once the owner has been notified that the system is classified as HIGH. The owner is not responsible for matters outside its control, but is responsible if the breach persists after a request to cure.
Two responsible statements are required: one submitted with the access and connection application and another submitted to the Ministry for Digital Transformation and Public Function (MTDFP) before hosting the first HIGH system. The first is a requirement for the permits (Article 4.1.a), so it appears to be required even for data centres that will never host HIGH systems, despite what the explanatory memorandum suggests.
Three serious uncured breaches may result in the loss of the access and connection permit. A ministerial order will implement these rules within six months; if it is not approved, the conditions will be directly applicable.
Projects holding permits but not yet connected (Transitional Provision 5) that have already been notified that they host HIGH systems will have twelve months to comply, without their permit lapsing. Article 5 also applies to European strategic projects (Transitional Provision 2).
The digital sovereignty obligations are no longer a universal requirement for all data centres and are now focused on data centres hosting HIGH-category systems.
However, the reform raises new issues, including the following:
Background: The Draft RD required Class «A» of the European label for PUE (power usage effectiveness) and WUE (water usage effectiveness) and, during the transitional period, PUE ≤ 1.15 and WUE ≤ 0.1. Falling within Class «B» or lower for two consecutive years was deemed a serious breach, and the cure period (not less than three months) could be shortened where there was a serious and immediate risk.
The New Draft requires both requirements to be Class «A», as follows: (i) for water usage effectiveness, the class under the European label; and (ii) for energy efficiency, the highest category resulting from the normalisation to be carried out according to use, the development or introduction of technologies and the different climates across Spain (to be implemented by ministerial order under the new Additional Provision 4).
As a transitional measure (Transitional Provision 6), until the European labelling system and the energy efficiency methodology apply, the requirements are set at: PUE 1.25 (raised compared with the Draft RD); and WUE remains at 0.1.
These levels must be achieved six months after the data centre starts operating and will be verifiable from the first full calendar year thereafter.
In addition, the new Transitional Provision 8 provides for a longer transitional period for compliance with the energy efficiency requirement: data centres that have signed the ATR contract before 1 January 2029 must comply, until 31 December 2031, with a PUE ≤ 1.25 “in substitution for” the values in Article 6.1 and Transitional Provision 6. From 1 January 2032, they will be subject to Article 6.1 under the climate normalisation methodology.
The new PUE of 1.25 is more achievable, and climate normalisation addresses the industry’s criticism that a single value penalised warmer locations.
However: (i) the reference to the “highest category” resulting from a methodology not yet approved creates uncertainty as to the final threshold applicable from 2032 (or from when the European label applies); (ii) Transitional Provision 8 only mentions PUE, so it is unclear whether, while it is in force, the data centres concerned are released from WUE ≤ 0.1 or whether this remains applicable under Article 6.1; and (iii) given that Transitional Provision 6 already sets a PUE of 1.25 until the European label applies and, for energy efficiency, until the methodology under Additional Provision 4 is rolled out, the added value of Transitional Provision 8 lies mainly in guaranteeing that value until a fixed date (31 December 2031) for data centres with an ATR contract signed before 2029.
Background: Under the Draft RD, the data centre had to cover 80% of its consumption through self-consumption or PPAs with renewable producers located in Spain, with facilities commissioned no more than 18 months before the data centre starts operating. The industry argued that this period and the restriction to renewable energy facilities were excessive.
The New Draft maintains the 80% threshold but introduces the following changes:
In our view, the New Draft makes it easier to meet the additionality requirement by including new alternatives and a longer compliance period.
Notwithstanding these changes, some questions remain:
Background: In the Draft RD, the 80% hourly backing could only be achieved through self-consumption or PPAs with renewable producers. Surcharges were graduated in three bands (10%, 30% and 50%) according to the percentage of non-compliant hours in the month, increasing by 10 percentage points for each consecutive month of non-compliance.
The main changes in the New Draft are as follows:
These changes, and in particular the inclusion of storage, were requested by the industry and fit the 24/7 consumption profile of data centres.
The new metric, based on hourly energy, introduces gradation within each hour: partial backing is no longer treated in the same way as a total lack of backing. However, as it is an arithmetic mean, all hours carry equal weight, regardless of the volume consumed in each. The upper bands are more onerous (70% and 100%, compared with the previous maximum of 50%). By contrast, the move to annual escalation significantly softens the progression in the event of repeated non-compliance.
The drafting, however, raises several questions:
There are no substantial changes to the grounds for loss (the procedural changes to Article 11 are analysed below). However, Article 11.1 now lists the grounds under letters a) and b) and deletes the conjunction “or” that framed them as alternatives, which could raise the question of whether they must occur cumulatively. The context suggests that they are alternatives, although the wording could be improved.
Background: The Draft RD required a minimum term of ten years, execution as a public deed (escritura pública), express reflection of the relationship between the data centre and the facilities, and the exclusion of matching arrangements based solely on guarantees of origin.
In the New Draft, the minimum term is reduced to six years, and an obligation on the producer of the associated renewable energy is added to redeem, at least once a year, the associated guarantees of origin before the CNMC, stating the data centre’s CUPS (the Spanish universal supply point code). The remaining requirements are maintained, in particular, execution as a public deed, the invalidity of financial contracts entered into by the parent company or group that do not reflect the relationship with the data centre, and the exclusion of products traded on organised markets whose renewable origin is evidenced solely by guarantees of origin.
The shorter PPA term makes it easier to find producers willing to sign and to negotiate better prices, given that a ten-year commitment is unusual in the market. The new obligation on guarantees of origin works as a “certificate of provenance”: it records before the CNMC that the renewable energy under that contract has been allocated to that specific data centre, identified by its CUPS, and to no one else.
However, the obligation to redeem the guarantees of origin annually falls on the producer, not on the data centre. It is therefore advisable for the PPA to provide for it expressly and to set out what happens if the producer fails to comply.
Under the new Transitional Provision 1, for the five years following the entry into force of the Royal Decree, data centres may meet the technical requirements to participate in the Automatic Power Reduction System (SRAP). In exchange, hourly matching is required on a progressive basis, instead of the 80% hour-by-hour requirement in Article 9: (i) until 31 December 2028, 60% of the energy consumed in the hours of period P1 corresponding to the relevant voltage level; and (ii) from 1 January 2029 until the end of the transitional period, 70% in P1 and 60% in P2.
Requirements to opt into the SRAP:
These data centres are considered preferential, as they are the first to respond to the readiness signal to reduce consumption.
To opt into this transitional regime, a responsible statement must be submitted together with the application for access and connection permits. Only facilities that start operating before 31 December 2030 may do so.
Withdrawal from the SRAP (voluntary or due to non-compliance) or failure to meet the requirements of operating procedure 3.11 may result in the loss of the access and connection permits (under Article 11, following notification by the system operator). Until the loss of the permit is declared, the system operator may adopt the measures it considers necessary, including disconnection of the facility, without any right to compensation and without this counting for quality of supply purposes. After the five years, the hourly matching requirement in Article 9 applies in full.
The new regime offers a significant flexibility incentive for meeting the hourly matching requirement in the early years. However, it requires flexibility and the ability to reduce consumption to zero. This commitment will be difficult to reconcile with the availability levels committed to customers, unless the data centre has its own backup (storage or self-consumption).
Questions also remain as to:
The new Transitional Provision 2 creates a specific regime for data centres that jointly meet the following requirements:
Intermediating or reselling capacity controlled from third countries is not sufficient.
Application of this regime also requires two favourable and binding reports: (i) from the MTDFP, on the sovereignty conditions; and (ii) from the system operator, on the impact on the security of the electricity system. The regime applies once both reports are on the network operator’s file.
The special rules affect Articles 6 to 9:
Non-compliance leads to the surcharges and loss of permits under Articles 10 and 11.
Requesting the MTDFP report within the month following entry into force (or following the application, if later) suspends the transitional periods until both reports are issued. If either report is unfavourable, the periods resume.
Article 5 (digital sovereignty) continues to apply.
The conditions must be maintained throughout the regime, and changes of ownership, control or operation must be notified within one month. If the Ministry declares, after giving the affected party an opportunity to be heard, that any condition is no longer met, the general regime applies after three months.
This regime is closely focused on Spanish bids for AI gigafactories, although it raises several issues:
Although the New Draft introduces significant improvements, some of the industry’s main concerns remain unaddressed:
Hourly matching. The requirement to cover at least 80% of consumption in each hour with renewable energy generated in that same hour is maintained. Admitting, for additionality purposes, existing photovoltaic facilities without a PPA and biomass facilities reaching the end of their regulatory life, as well as storage, facilitates compliance. However, it remains the requirement with the greatest impact on project costs, particularly in hours without solar production.
Transitional regime linked to the SRAP. It offers a more gradual route of entry. In exchange, it requires the ability to reduce consumption to zero and allows disconnection without compensation until the loss of the permit is declared. For infrastructure that operates continuously, it would be advisable to limit the duration and frequency of reductions and to specify the applicable safeguards. It would also be helpful to clarify what is required outside periods P1 and P2 and how the transition to the general regime will work after the five years.
Surcharges and loss of permits. Surcharges remain high: (i) for hourly matching, the top band reaches 100%; and (ii) for additionality, they range from 100% to 500%. The possible loss of the access and connection permits is also maintained. The text strengthens procedural safeguards. Even so, it would be desirable to clarify whether surcharges and loss of permits may be imposed concurrently, and how they fit within the enabling provision of Royal Decree-Law 7/2026.
Time horizon for the efficiency requirements. The PUE of 1.25 is guaranteed until 2031 only for data centres with an ATR contract signed before 1 January 2029. Thereafter, a climate normalisation methodology that has not yet been approved will apply. Given the long regulatory life of these infrastructures, the final text should set out the values that will be required as soon as possible.
European strategic projects regime. The regime makes sense given the digital sovereignty objectives it pursues. However, it is limited to initiatives launched before entry into force and does not specify how long its special rules will apply. Specifying that duration would provide greater legal certainty and help avoid differences in treatment between comparable projects.
Transitional periods and legal certainty. The three-month period for pending access applications (Transitional Provision 3) and the six-month period for projects that hold access permits but have not yet connected to the network (Transitional Provision 5) are maintained. If these deadlines are not met, the applications will be rejected or, in the case of permits already granted, the permits will lapse and the guarantees will be enforced. It would be helpful to clarify the position of data centres that, for reasons beyond the developer’s control, have passed connection tests but have not yet signed the ATR contract.
Other technical points. In our view, from a technical standpoint, it would be advisable to reinstate the definition of access capacity, which determines the 10 MW threshold, and to clarify whether financial or virtual PPAs are admissible where they reflect the relationship between the data centre and the generation facilities.
Ashurst Perkins Coie’s leading multidisciplinary data centre team can assist you with analysing the impact of the New Draft on your projects, project structuring and financing, the negotiation of PPAs and colocation agreements, and regulatory strategy. Please do not hesitate to contact us.
The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
Readers should take legal advice before applying it to specific issues or transactions.