You've received a force majeure notice. What now? - A practical guide for businesses on the receiving end of force majeure claims
Global disruption seems to be the new normal state of the world. Even regional events can trigger cascading effects across interconnected economies. From the Covid-19 pandemic to the Russia-Ukraine conflict and the Middle East crisis, businesses face rolling shocks that ripple across borders and supply chains. The consequences cut across industries: volatile energy prices, supply-chain breakdowns, project delays, and margin-squeezing cost escalation.
Against this backdrop, contractual disputes proliferate, testing contractual mechanisms and dispute resolution provisions. The unpredictable geopolitical landscape has focused attention on force majeure clauses. Force majeure notices now land with increasing frequency, and sometimes in volume. This creates time pressure and makes it hard to effectively manage responses.
If you receive one (or more) force majeure notices, you need a structured management and response process. Missteps may carry severe, potentially irreversible, consequences. This quick guide sets out what to do and what to watch out for.
It is not only geopolitical disruption that is testing commercial parties' agreements. The impact of increasingly extreme weather represents another uncertainty driving disputes. For discussion of the contractual implications of disruptive weather, see our article: Extreme weather: beyond the force majeure clause - How changing weather conditions will drive commercial disputes, and what you can do to prepare.
Many civil law systems recognise a doctrine of "hardship" or "material adverse change" grounded in good faith principles. This allows contracts to be renegotiated, adjusted or, in certain circumstances, terminated to address unforeseen circumstances that fundamentally alter the parties' bargain.
These systems also typically recognise force majeure as a freestanding principle. Although the precise requirements vary between jurisdictions, force majeure in civil law jurisdictions generally requires an event beyond the affected party’s control that could not reasonably have been foreseen or avoided, and that prevents that party from performing its contractual obligations. Depending on the applicable law and whether the impediment is temporary or permanent, force majeure may excuse or suspend performance of the affected obligations or, in certain circumstances, result in termination of the contract1.
Common law systems generally recognise no such principles. Parties will be held to, and must generally perform, their freely undertaken obligations, unless their contract contains a force majeure clause and they satisfy its conditions.
If a party successfully claims force majeure, its performance obligations may be suspended while the event continues. Prolonged or permanent force majeure may also result in termination under the terms of a contract's force majeure clause.
Courts and arbitral tribunals enforce force majeure clauses but construe them strictly, given the significant consequences of successfully invoking force majeure. Both the claiming party and the notice recipient must adhere carefully to the contract's terms. Wrongful reliance or unjustified refusal to perform may amount to repudiatory breach.
Notice recipients face their own pitfalls. Accepting an invalid notice could amount to an unintended waiver of your contractual rights. Rejecting a valid notice and terminating could expose you to significant damages claims.
So, what to do when you receive a force majeure notice?
A force majeure notice creates immediate time pressure, particularly if it affects your obligations to other parties in a contractual chain. Resist the urge to fire off a fast, substantive reply so you can move on to the next issue.
Instead, put in place a structured response process:
When acknowledging a force majeure notice, avoid language that could be read as accepting the claim, waiving rights, or otherwise prejudicing your position (for example, creating an estoppel). Avoid at this stage admitting that the notice is "in accordance with" the contract's force majeure clause or the applicable law. Keep your holding response factual and neutral. Indicate that you are reviewing your counterparty's claim and will respond substantively in due course.
The first step is to identify the basis on which force majeure is invoked, whether under the contract, the applicable law, or both. This will allow you to assess the notice against the requirements that apply to the claim.
For instance, non-compliance with contractual notice provisions can defeat a force majeure claim entirely. For this reason, whether a force majeure clause imposes a notification requirement (and/or reporting obligation) as a pre-condition to invoking force majeure is often a vigorously contested issue. It will turn on the proper interpretation of the precise language used by the parties.
The recent English decision of ADM Industries Centers Ltd v Inerco Trade SA [2026] EWHC 1873 (Comm) illustrates the point. The contract provided that performance would be suspended for force majeure events "provided that Sellers shall have served a notice on Buyers within 7 consecutive days of the occurrence". An arbitral tribunal ruled that compliance with this period was not a condition precedent, provided the buyer was not prejudiced by any delay. The English Commercial Court disagreed, holding that the wording was unmistakably the language of a condition precedent and served a desirable commercial purpose. If the sellers had not complied with the notice period (a question remitted to the tribunal), it followed that they had not properly invoked force majeure and their claim should fail.
On receiving a force majeure notice, check:
Remember that common law courts and arbitral tribunals construe force majeure clauses strictly according to the words used. If the clause refers merely to "war," then a "conflict" may not qualify. However, if, as is common, the clause references "war, declared or undeclared", then the position may be clearer. Similarly, where the clause requires performance to be "prevented" by the force majeure event, the fact that performance is merely "hindered" or costs have increased is unlikely to suffice.
Another area of uncertainty arises from the phrase "acts of God", which commonly appears alongside a list of specified natural events, such as "flood, drought, earthquake or other natural disaster". This creates several uncertainties. First, it may be unclear whether the specific instances are intended to be examples of a broader category of "acts of God", or whether "acts of God" are some different class of event, separate from those expressly listed. Second, the phrase "acts of God" may also add additional scope for dispute where the clause specifies that force majeure relief will be disapplied for events that should have been foreseen by the affected party: to what degree can an act of God ever be said to have been (reasonably) foreseeable?
Move beyond the paperwork and interrogate the claim on its merits:
Request detailed information from your counterparty to support their force majeure claim and its impact on performance. Request a timeline setting out when the event occurred, when performance was affected, what steps were taken and when, and the event's anticipated duration. Ask for evidence of mitigation efforts. This helps you decide whether to accept or reject the claim. Requiring your counterparty to set out a detailed written account may prove valuable should a dispute arise down the line.
The consequences of getting your response wrong run in every direction.
| Action | Risk |
|---|---|
| No substantive response. | May constitute acquiescence to the claim or waiver of your rights. May also create an estoppel where applicable. |
| Accepting an invalid force majeure claim. |
May waive your contractual rights or damages claims, even though the force majeure claim is invalid. |
| Rejecting a valid claim and terminating contract for breach. |
Wrongful termination could constitute repudiatory breach and expose you to significant damages, potentially the full contract value. |
Take legal advice before committing to a position. Consider whether meeting your counterparty to discuss an amendment to the contract, reflecting the new commercial reality, offers a better option than confrontation.
A counterparty's upstream force majeure claim may cascade into your downstream obligations. However, force majeure clauses rarely match across related contracts. They may define force majeure events differently or impose different notice, foreseeability or mitigation requirements. There is, therefore, a (potentially complex) exercise to assess whether a force majeure event relied on by your counterparty under one contract, will allow you to trigger the force majeure provisions in another agreement.
Steps to take:
Energy, infrastructure and natural resources contracts face particular exposure. Against a backdrop of volatile energy prices and supply-chain dependencies, force majeure claims often involve high-value, long-term commitments with complex termination provisions. Government action, sanctions, export restrictions and disruption to critical supply or transportation routes may also give rise to force majeure issues, depending on the contractual terms.
Some oil and gas infrastructure contracts permit termination where prolonged force majeure prevents works for extended, aggregate periods. However, this carries significant financial consequences, including potential obligations to pay for completed but unsettled work.
Various issues may require input from experts, including, for example, challenging whether a claimed force majeure event is causative of a counterparty's inability to perform. Consider early whether such input may be required and, if necessary, engage a suitable expert early on. Particularly in specialised energy markets, such as the gas market, the pool of potential experts may be small, with conflicts of interest further impacting availability.
An oil or gas company that sees its ability to deliver reduced, but not wiped out, by a force majeure event, may be obliged to share whatever volumes it has available among its various buyers. This would typically be in proportion to the buyers' contractual entitlements. Without this obligation, a seller might elect to fully perform under its most valuable contract(s), while declaring force majeure under others. However, contracts often create complex arrangements covering such scenarios, whose interpretation may well be disputed.
Authors: Philip Chong, Partner; Sylvia Tee, Partner; Cameron Cuffe, Partner; Tammam Kaissi, Partner; and Alex Hiendl, Senior Expertise Lawyer.
The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.