Data Centres in Light of the Royal Decree: Key Decisions and Outstanding Issues
On Saturday, 21 November 2026, Royal Decree 1032/2026 was published in the Official State Gazette. This decree regulates the requirements for energy sustainability, environmental sustainability, resilience, and digital sovereignty applicable to data centres (the Royal Decree), which had been approved by the Council of Ministers the previous day.
In previous posts, we analysed the Draft Royal Decree submitted for public consultation and the version forwarded to the Council of State (the Final Draft). The final text incorporates many of the essential observations made by the Council of State in its Opinion 1041/2026, dated 6 November (the Opinion), which explains many of the changes outlined below.
In this post, we summarise the regime that was ultimately approved, a timeline of applicable deadlines, and the main practical issues and recommendations.
IMPORTANT NOTICE REGARDING THE IMPLEMENTATION OF THE ROYAL DECREE
The Royal Decree entered into force on 22 November 2026. However, appeals have already been filed against it, seeking injunctive relief for its immediate suspension (among others, by the association SpainDC and several regional governments due to the potential infringement of their constitutional competences).
In any case, unless a precautionary measure is granted or the text is amended, the various obligations are directly enforceable and the transitional deadlines apply. Furthermore, the sanctioning regime arises from Royal Decree-Law 41/2026.
Unlike the Final Draft, which provided for entry into force twenty days after its publication, the Royal Decree entered into force on the day following its publication in the Official State Gazette (BOE), that is, on 22 November 2026 (Final Provision 7). For the purposes of ongoing data centre projects and applications for capacity allocation, this date determines the initial term of all transitional deadlines, which—based on a conservative interpretation—are identified below:
The Royal Decree renumbers the articles (the former Articles 8 through 14 become Articles 7 through 13); the references in this note correspond to their final numbering.
| Subject | Latest Draft | Royal Decree |
| Compliance (Articles 4, 6, 7, and 8) |
Responsible statements. The A&C permit required compliance with renewable energy requirements (system share > 90% or additionality and hourly matching). |
Commitment statements regarding efficiency, additionality, and hourly matching. Renewable generation at 90% falls under DA 6. Responsible statements are reserved for digital sovereignty |
| Digital sovereignty (Art. 5) |
Prohibition on hosting HIGH-category information systems unless three conditions are met. Loss of permit due to serious non-compliance that has not been remedied. A ministerial order would approve the models; in the absence of such an order, the conditions would become directly enforceable. |
The conditions are a requirement for obtaining permits and must be maintained throughout the hosting of HIGH information systems. The loss of the permit as a specific regulatory consequence is eliminated: the MTDFP reports non-compliance to the responsible public entities, without prejudice to Article 69.4 of Law 39/2015 and the sanctioning regime. The deadline for approving the responsible statement form is eliminated: the order under Transitional Provision 6 approves the forms, but failure to approve them does not affect their enforceability. |
| PUE / WUE (Art. 6 and Transitional Provision 6) |
PUE ≤ 1.25 and WUE ≤ 0.1 are required within six months after the data centre starts operating. |
Same values. However, the deadline for compliance is extended: PUE must be met within two years and WUE within one year. Non-compliance requires a corrective action plan. |
| Deviations from additionality and hourly matching (Art. 9) |
Percentage surcharges on transmission fees and charges (100%–500% and 10%–100%) with a +10 percentage point increase for each consecutive year. |
There is no surcharge, but deviations require compensation in €/MWh consumed:
|
|
Loss of permits (Art. 10) |
Loss due to significant and repeated non-compliance with renewable energy requirements (five consecutive years) and following a ruling for serious non-compliance with digital sovereignty or efficiency requirements (Articles 5.6 and 6.6). | The regulatory regime governing the loss of permits is removed, and reference is made to the sanctioning regime under Law 24/2013 and other laws, approved by Royal Decree-Law 41/2026. Suspension or revocation is only required in accordance with the cases and procedures established by law. This addresses the key observation in the Opinion. |
| SRAP (Transitional Provision 1) | Disconnection without compensation and possible loss of the permit. |
Same schedule (60% in P1 through 2028; 70% in P1 and 60% in P2 starting in 2029), but based on the energy consumed each hour. Statement of commitment substituted responsible statement. “Necessary and proportionate” measures; disconnection for the strictly necessary period and without prejudice to the liability regime. |
| Strategic projects (Transitional Provision 2) | EU initiatives whose primary purpose is digital sovereignty or applications submitted by the Government of Spain. The preamble referred to a limited timeframe, but the articles of the law did not specify it. Non-compliance is subject to surcharges and the loss of permits. |
Projects, proposals, applications, or bids in European calls for proposals whose purpose is to strengthen digital sovereignty, without requiring it to be the primary purpose. A limited timeframe has still not been established. Energy efficiency and additionality criteria adjusted according to the date of commissioning. The matching criterion is equal to the system’s renewable energy share from the previous year. Class C for facilities with permits in effect upon entry into force, regardless of their date of commissioning. Non-compliance is subject to compensation and penalties. |
The content of the Royal Decree is analysed below, with a brief overview of its final wording and the most significant differences from previous drafts.
The scope of application covers operating entities or, if there is no separate operating entity, the owners of data centres that have applied for or intend to apply for access and connection permits in accordance with Royal Decree 1183/2020. The obligations apply to centres with an access capacity threshold of 10 MW or more and to groups of centres located at the same site and under the same ownership that reach that capacity on an aggregate basis. In facilities with ICT equipment whose primary activity is not a data centre, only the capacity dedicated exclusively to that activity must be considered.
The threshold does not apply to Article 5 (digital sovereignty), which applies regardless of the access capacity.
The reporting and disclosure obligations under Article 13 apply to facilities with information technology power (IT power) of 500 kW or more, regardless of their access capacity. IT power is defined as the electrical power demand of the installed information technology systems, determined in accordance with Article 2 of Delegated Regulation (EU) 2024/1364 (Art. 3.j). The Royal Decree also applies to transmission and distribution system operators, within the scope of their respective competences.
The following are excluded: (i) facilities dedicated exclusively to defence, civil protection, and public safety; and (ii) facilities of state public sector entities that are critical operators under Law 8/2011, or that are affiliated with such entities.
The obligations do not always fall on the same entity. Those related to digital sovereignty (Art. 5) always fall on the owner of the data centre. The remaining obligations—energy and water efficiency (Art. 6), additionality (Art. 7), hourly matching (Art. 8), and publicity (Art. 13)—as well as the SRAP regime (Transitional Provision 1), fall on the operating entity or, if there is no separate operating entity, on the owner of the data centre.
Changes from the Last Draft: Article 2.1 now expressly includes within its scope of application data centres with applications that have not been approved, data centres with applications suspended due to capacity constraints, and data centres with permits granted but not yet connected. The rest of Article 2 remains unchanged.
Considerations for the Sector
The 10 MW threshold excludes a significant portion of smaller-scale projects from the grid access requirements.
The following issues, among others, remain unresolved:
The granting of permits that were not obtained prior to the entry into force of the Royal Decree, or that are applied for thereafter, requires, in addition to the provisions of Chapter III of Royal Decree 1183/2020: the submission of (a) a responsible statement regarding digital sovereignty under Article 5.4; (b) a statement of commitment regarding energy and water efficiency or, where the European labelling system applies, the project’s European label; and (c) a statement of commitment regarding additionality and hourly matching.
Additionally, the Royal Decree includes in its First Additional Provision a regime governing the effects of access requirements in demand-capacity auctions, as well as the rejection of applications in the event that the aforementioned requirements of the Royal Decree are not met.
Changes from the Latest Draft: The Latest Draft required, as a condition for granting the permit, compliance with “the requirements relating to renewable energy”—that is, having a renewable share of the system above 90% or meeting the requirements for additionality and hourly matching. The Royal Decree removes this reference and only requires the submission of a statement of commitment regarding additionality and hourly matching. Responsible statements regarding efficiency are also replaced by statements of commitment.
Considerations for the Sector
Replacing responsible statements with statements of commitment makes it easier to obtain permits but shifts the risk to the operational phase: compliance is verified throughout the facility’s useful life, and deviations or non-compliance result in compensation (rather than surcharges) under Article 9 and, where applicable, penalties. Points to consider:
Data centres are not subject to digital sovereignty requirements, unless they are expressly notified that any of the information systems they host is classified as HIGH under the National Security Scheme (Annex I of Royal Decree 311/2022). Systems that process classified information are also exempt.
Data centres subject to digital sovereignty must meet three conditions to obtain permits and must maintain compliance for the duration of the hosting arrangement:
The data controller must communicate these conditions to its customers, suppliers, and direct subcontractors, although it shall not be liable for matters beyond its direct or contractual control.
For the purposes of this article, along with the application for an access and connection permit, the obligated party must submit a responsible statement to the network operator and the MTDFP affirming that it does not host HIGH-category information systems or, if it does, that it complies with the conditions. This statement must also be submitted to the MTDFP before hosting a system of that category for the first time. The declaration shall cover all systems within a single data centre and must be updated whenever the declared conditions change substantially, as well as whenever the list of affected systems changes.
Changes from the Last Draft: see the table of changes; additionally: (i) the first responsible statement may be limited to stating that no HIGH-category systems are hosted, and (ii) the conditions are without prejudice to the stricter location requirements established by law, in particular, Article 46 bis of Law 40/2015.
Considerations for the Sector
The regime is now more proportionate: it does not specifically provide for the loss of the permit as a consequence, although revocation remains possible through legal channels (Art. 10). It is advisable that contracts to be signed (including, among others, colocation agreements) include the customer’s obligation to disclose HIGH-category information systems and the allocation of liabilities.
The Royal Decree maintains the energy and water efficiency requirements for data centres but extends the compliance deadline.
The operating entity or, failing that, the owner of the data centre must demonstrate Class “A”: (a) in water efficiency (WUE); this class corresponds to that of the European label; and (b) in energy efficiency (PUE), the highest category resulting from the climate normalisation methodology to be approved by order of the Ministry for Ecological Transition and the Demographic Challenge (MITECO) (Fourth Additional Provision). Certification is provided through the European label or, failing that, for projects that have not yet become operational, through a statement of commitment.
In accordance with Transitional Provision 6, until the European labelling system is implemented (foreseen for August 2027) and, in the case of PUE, until the methodology of the Fourth Additional Provision is rolled out, a PUE ≤ 1.25 and a WUE ≤ 0.1 are required.
Energy efficiency levels (PUE) must be achieved within two years of the data centre becoming operational, and water efficiency levels (WUE) within one year. These levels are verifiable starting with the first full calendar year following operation. Thereafter, by 15 October of each year, the European label or, on a transitional basis, an annual declaration certifying compliance with these values must be submitted to MITECO and MTDFP (DT 6).
However, data centres with an ATR formalised before 1 January 2029 must comply with a PUE ≤ 1.25 until 31 December 2031, in lieu of the values specified in Article 6.1 and Transitional Provision 6. From 1 January 2032 the standardisation methodology will apply (Transitional Provision 8).
During the transitional period covered by Transitional Provision 6, compliance is demonstrated by a statement of commitment submitted with the application to the grid operator and, simultaneously, to MITECO and MTDFP. If an infringement is detected, surcharges will no longer be imposed, but a corrective action plan will be required. If the plan is not submitted or implemented, the matter will be referred to the sanctioning entity. The applicable sanctioning regime is foreseen in Law 18/2014, of October 15, approving urgent measures for growth, competitiveness, and efficiency (based on the amendment approved through Royal Decree-Law 41/2026, also published in the Official State Gazette (BOE) on 21 November 2026, and ratified by the Standing Committee of the Congress (Diputación Permanente del Congreso de los Diputados), the body with authority while Parliament is dissolved).
Changes from the Last Draft: In addition to the deadlines and the new corrective action plan identified in the table of changes, the provision authorising the updating of PUE/WUE values by order has been removed.
Considerations for the Sector
The operating entity or, failing that, the data centre owner must demonstrate that it covers 80% of its total consumption through (a) self-consumption (Royal Decree 244/2019) or (b) one or more renewable electricity purchase agreements (PPAs) with producers who own renewable energy facilities and storage facilities (batteries) located in Spain. Specifically, the PPAs must meet the requirements set forth in Article 11 (see the section “How are PPAs regulated (Art. 11)?”).
The aforementioned facilities (self-consumption, renewable energy, or storage) must have a commissioning certificate issued no more than 36 months prior to the data centre’s entry into operation (which is identified by the execution of the ATR contract) or the first use of the energy (60 months under the European strategic projects regime of the Second Transitional Provision). Also, additionality may be demonstrated through:
The operating entity or owner must submit to the grid operator, along with the permit application, a statement of commitment to compliance and, where applicable, its plans for the deployment and expansion of renewable capacity. Once operational, consumption is limited at all times to the amount that can be supported by additional generation. The system operator is responsible for calculating the deviation and compensation on a monthly basis. In the event of non-compliance, the compensation provided for in Article 9 applies, without prejudice to the sanctioning regime (Article 10).
If the share of renewable generation in the national electricity system exceeds 90% in year n-2 (where n is the year of the permit application), the additionality and hourly matching requirements are deemed to have been met, but the permit is subject to a maximum annual number of hours of grid consumption (DA 6).
Changes from the Last Draft: the substantive requirements remain in place (80%, 36-month window, repowering, biomass, photovoltaic exception, and Transitional Provision 7); annual verification is replaced by a centralised monthly calculation by the system operator. For self-consumption, the facility must ensure the availability of the necessary metering equipment (Art. 7.4).
Considerations for the Sector
The final text does not alter the structure of the requirement, so the availability of new renewable generation will continue to be a critical factor in project timelines and will encourage collaboration between data centre developers and renewable energy project developers.
To be noted:
The operating entity or, failing that, the owner of the data centre must ensure that at least 80% of the energy consumed in each hour is backed by an equivalent volume of renewable electricity generated during that same hour, through (a) self-consumption (Royal Decree 244/2019), (b) PPAs with producers who own renewable energy facilities, or (c) storage facilities. Unlike the additionality requirement (Art. 7), the hourly matching requirement (Art. 8) does not expressly require that the facilities linked to the PPAs be located in Spain.
The percentage is reduced if the alternative regime linked to the automatic power reduction system (SRAP) is applied (Transitional Provision 1), and, in the case of European strategic projects, it is equal to the system’s renewable share from the previous year (Transitional Provision 2).
Energy injected by the associated storage facility is presumed to be renewable, but specific rules apply depending on whether the storage is considered hybrid or not associated with generation (Art. 8.5).
A statement of commitment to comply with the operator’s renewable energy deployment and expansion plans—and, where applicable, storage plans—must be submitted along with the permit application. The system operator will be responsible for calculating the deviation and compensation on a monthly basis. In the event of non-compliance, the compensation provided for in Article 9 applies, without prejudice to the sanctioning regime (Art. 10).
Changes from the Last Draft: The 80% hour-by-hour consumption requirement and the storage rules remain in place. However, as with the additionality requirement, verification is now a centralised monthly calculation performed by the system operator.
Considerations for the Sector
The 80% hourly matching is expected to be the requirement with the greatest economic impact. Storage helps meet this requirement but does not prevent the oversizing of renewable capacity during hours without solar generation.
The Royal Decree replaces the percentage surcharges with a compensation mechanism, in accordance with Additional Provision 1 of Royal Decree-Law 7/2026. The compensation is accrued for deviations from the additionality and hourly matching levels set forth in Articles 7 and 8, and the income is used to cover the costs of capacity mechanisms (Article 13 of Law 24/2013) and, where applicable, other additional costs for consumers.
This compensation is calculated by multiplying a value in €/MWh by the energy consumed by the data centre in the year prior to the billing year, and not just by the uncovered portion. For clarification purposes, regarding additionality, the portion is determined by comparing the additional generation with the energy consumed by the data centre in the calendar year prior to the billing year. On an hourly basis, it is determined by the total percentage deviation relative to the total number of hours in the month.
The total deviation percentage is the arithmetic mean of the hourly percentages for the month: 0% if backup reaches 80% and 100% if there is no backup, with linear interpolation between these two extremes.
Simply put: each hour receives a deviation score, which is zero if at least 80% of that hour’s consumption is covered by renewable energy and increases proportionally as coverage decreases, up to 100% when there is no coverage at all (for example, an hour covered at 40%—half of the required amount—has a deviation of 50%); the average of all hours in the month determines the applicable bracket. The grid operator with whom the ATR contract was signed issues a provisional monthly bill based on the system operator’s calculation (Articles 7.5 and 8.4).
In addition, the system operator also provides the distribution network operator, when necessary, with generation data (Art. 9.2). The compensation is passed on directly to the end consumer when the ATR contract has been signed with the distributor, or to the retailer when the ATR contract is included in the supply contract (Art. 9.4). By March 31 of each year, the Secretary of State for Energy must approve, by resolution and upon the proposal of the system operator, the final offsets for the previous calendar year, and the operators will adjust any differences on the next bill.
Changes from the Last Draft: In addition to what is indicated in the table, the monthly bill is now provisional and is adjusted after the final settlements are approved.
Considerations for the Sector
With the Royal Decree, the cost of deviations is much more predictable and easier to model. The Final Draft applied percentage surcharges (of up to 500% on top of the base amount), which could multiply that bill several times over. The Royal Decree, on the other hand, sets a fixed amount in €/MWh consumed, with a maximum of €41 /MWh that would only be reached if the data centre has additional generation of less than 20% (25 €/MWh) and, at the same time, a matching deviation of 50% or more (16 €/MWh).
However:
In accordance with the requirements of the Opinion, the Royal Decree eliminates the specific regime regarding the loss of access and connection permits that was included in the Final Draft. Failure to comply with the requirements will be penalized, pursuant to the amendment approved by Royal Decree-Law 41/2026, in accordance with Law 24/2013 on the Electricity Sector; Law 18/2014, regarding energy and water efficiency; Royal Decree-Law 7/2026, regarding digital sovereignty; and other applicable regulations having the force of law. The suspension or revocation of permits may only be ordered in the cases, within the limits, and through the procedures legally established in the aforementioned regulations.
Changes from the Last Draft: in addition to what is set forth in the table of changes, the limitation on the National Commission for Markets and Competition’s (CNMC) review of access disputes (Art. 12)—which did not review the substantive assessment under Article 5—has been removed; it now resolves such disputes in accordance with Article 33.3 of Law 24/2013, without that limitation.
Considerations for the Sector
The Opinion characterized the surcharges and the loss of permits as genuine sanctions and concluded that the First Additional Provision of Royal Decree-Law 7/2026 was a blank reference without sufficient legal basis.
Consistent with this, the Royal Decree eliminates the loss of permits as a consequence provided for in the Royal Decree itself, but does not eliminate the risk to the continuity of projects. Article 10 merely refers to the statutory sanctioning regime, and that regime was supplemented on the same day by Royal Decree-Law 41/2026 (BOE No. 290, of 21 November, 2026), effective as of 22 November 2026, through the amendment of the following laws:
Ratification. Royal Decree-Law 41/2026 is currently in force but must be ratified. Otherwise, the sanctioning regime set forth in the Royal Decree may become void.
The characteristics of PPAs for the purposes of the Royal Decree have not changed. Article 11 requires that PPAs used to demonstrate additionality and hourly matching identify the parties, the associated facilities, the formula, and the projected volume of coverage, and, in particular: (i) expressly reflect the relationship between the facility and the associated installations; financial contracts of the parent company or group that do not reflect this relationship are not valid; (ii) not be based on hedges in organised markets where the renewable origin is certified solely by guarantees of origin; and (iii) have a minimum term of six years and be formalised in a public deed, which must be submitted to the grid operator along with the permit application.
The owner of the generation facility must redeem the guarantees of origin, at least annually, with the CNMC, indicating the data centre's universal supply point code (CUPS).
Considerations for the Sector
Article 11 remains unchanged from the Final Draft but imposes conditions on the structuring of PPAs. To be noted:
For five years following the Royal Decree’s entry into force, the operating entity or, failing that, the owner of the data centre may choose to meet the technical capacity requirements necessary to participate in the SRAP.
In exchange, the hourly matching specified in Article 8 is required on a phased basis: (i) until 31 December 2028, 60% of the energy consumed in each hour of the P1 time period corresponding to its voltage level for the payment of surcharges; and (ii) from 1 January 2029 until the end of the transitional period, 70% in each hour of P1 and 60% in each hour of P2.
The data centre must be registered in the SRAP (Operating Procedure 3.11, the technical standard that governs it) and be capable of reducing its consumption to zero when ordered to do so by the system operator in the event of a contingency that compromises system safety criteria. Facilities covered by this provision are given priority in the dispatch order for resolving technical constraints; that is, they are the first to respond to the reduction signal.
To qualify for the program, the operating entity or the facility owner must submit to the grid operator, along with the application for access and connection permits, a statement of commitment to compliance; only facilities that become operational before 31 December 2030 are eligible.
If a data centre is removed from the SRAP—whether voluntarily or due to a breach related to its participation—or fails to meet the participation requirements of Operating Procedure 3.11, the system operator may take the necessary and proportionate measures to safeguard system security, including disconnection by opening the circuit breaker for the time strictly necessary. The disconnection does not count toward supply quality metrics. All of the foregoing is without prejudice to the applicable liability regime. The system operator shall notify the General Directorate of Energy Policy and Mines of the withdrawal or non-compliance. Five years after the effective date (22 November 2031), the hourly matching requirement set forth in Article 8 (at least 80% hourly coverage) shall become mandatory.
Changes from the Last Draft: see the table of changes.
Considerations for the Sector
The changes reduce the legal risk of disconnection, but the regime continues to require that the data centre be able to reduce its consumption to zero when the system operator sends the activation signal. The following issues, among others, remain unresolved:
In line with the Final Draft, DT 2 establishes a specific regime for data centres considered strategic that cumulatively meet the following requirements:
For these purposes, the mere intermediation or reselling of capacity controlled from third countries does not satisfy the above requirements.
This regime requires favourable and binding reports from the MTDFP and the system operator. If the MTDFP report is requested within the month following the entry into force (or the submission of the application, if later), the deadlines set forth in the Transitional Provisions 3 to 5 are suspended.
The specific provisions of this regime apply to Articles 6 through 8:
Non-compliance gives rise to the compensation provided for in Article 9 and the penalty regime; Article 5 remains applicable.
Changes from the Last Draft: the regime applies to any project, proposal, application, or bid submitted in response to the call for proposals (not only EU initiatives or applications from the Government of Spain), and it is sufficient that its purpose be to strengthen digital sovereignty—it need not be the “primary” purpose. The hourly matching is set at the quota specified in the 6th Additional Provision of the previous year; failure to comply is subject to compensation and penalties. However, neither the Final Draft nor the Royal Decree specifies the duration of the regime.
Considerations for the Sector
The regime provides legal certainty for eligible projects, but its practical scope is limited: it applies only to calls for proposals issued prior to its entry into force, and most data centres will remain subject to the general regime. For those eligible, it is important to note that the requirement that no third country have a decisive influence—whether direct or indirect—and the prohibition on the resale of capacity necessitate a review of the chain of control, shareholder agreements, and operating and hosting contracts.
Although the sector has expressed its opposition, it is still too early to assess the actual and economic impact of the Royal Decree on the sector’s operations, which will depend on how the new requirements are applied in practice and on the outcome of the announced legal challenges. Based on the published text, we highlight the following:
Considerations for the Sector
The elimination of surcharges and their replacement with compensation in €/MWh makes the cost of deviations more manageable; efficiency deadlines are more generous; and the digital sovereignty regime is more clearly defined. However, regulatory risk is not reduced; rather, its source has shifted: the loss of permits is no longer a direct consequence of the Royal Decree, but Royal Decree-Law 41/2026, already in force, introduces new infringements into Law 24/2013 with significant penalties, including the suspension of permits as an ancillary penalty.
In our view, the following issues, in particular, remain unresolved:
Ashurst Perkins Coie has a leading multidisciplinary team specialising in data centres that can assist you in analysing the impact of the Royal Decree on your projects, managing transition periods, structuring and financing projects, negotiating PPAs and colocation agreements, and developing regulatory and litigation strategies. Please do not hesitate to contact us.
This note is for informational purposes only and does not constitute legal advice. All intellectual property rights in its content belong to Ashurst Perkins Coie. Its reproduction, publication, distribution, or dissemination, in whole or in part, by any means, is prohibited without our prior written consent.
The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
Readers should take legal advice before applying it to specific issues or transactions.