Another step forward for Australia's Domestic Gas Reservation Scheme

Solar thermal power plant with thousands of mirrors in curved rows across a desert at sunset, mountains on the horizon

    What you need to know

    • The bills to implement Australia's Domestic Gas Reservation Scheme passed the House of Representatives on 29 October 2026. On 11 November 2026, the Senate Economics Legislation Committee recommended that the Senate pass the bills without amendment.
    • As expected, exporters of liquefied natural gas (LNG) will need an export licence from 1 January 2028 and must meet a domestic supply obligation (DSO) of 20% of their LNG exports (unless varied). The Australian Energy Regulator (AER) will administer and enforce the scheme. The Energy Minister will also have an expanded role.
    • Export contracts made on or before 22 December 2025 will not require amendments to expressly include the DSO conditions, but will not be exempt from this requirement if they are renewed or extended.
    • It is still unclear how the AER's demand and supply forecasts for the target aggregate supply will be calculated. The method is yet to be determined and must include any factors the Energy Minister specifies. Until then, stakeholders may find it difficult to settle their strategies and compliance approach.

    What you need to do

    • Check your contracts for renewal or extension rights. A contract renewed or extended after 22 December 2025 loses "existing contract" status.
    • Decide whether to apply for a DSO adjustment determination. Applications must be made before 31 December 2027.
    • Check that your group and sales structures maintain a continuous interest in gas you intend to count towards your DSO.
    • Prepare for the Gas Market Code changes starting on 1 July 2027.
    • Watch for the Senate's vote on the bills and the detailed rules still to be made.

    Introduction

    The Australian Government continues to develop the framework for the Domestic Gas Reservation Scheme ahead of the licensing and supply obligations starting on 1 January 2028. On 14 October 2026, the bills to implement the Domestic Gas Reservation Scheme were introduced to Parliament and passed the House of Representatives on 29 October 2026. On 11 November 2026, the Senate Economics Legislation Committee recommended that the Senate pass the bills without amendment. This follows public consultations on the exposure drafts in June and September this year, where industry stakeholders were invited to make submissions on their legal and commercial views on the proposed landmark legislation.

    The bills contain a number of changes from the exposure drafts. Most changes simply clarify the drafting, but some have real commercial and legal implications as the Domestic Gas Reservation Scheme moves closer to becoming reality. This article flags the key changes between the exposure drafts and the bills, as well as the commercial and legal implications.

    Domestic Gas Reservation Scheme

    The Domestic Gas Reservation Scheme bills comprise the Domestic Gas Reservation Bill 2026 (the Principal Bill), the Domestic Gas Reservation (Consequential Amendments) Bill 2026 (the Amendments Bill) and the Domestic Gas Reservation Levy Bill 2026 (the Levy Bill). The three bills together deliver the Government's proposed Domestic Gas Reservation Scheme.

    • The Principal Bill introduces a licensing regime and the DSO, which requires exporters of LNG to contribute to domestic gas supply. From 1 January 2028, each export licence holder must supply each domestic gas market it exports from with gas equivalent to 20% of the energy content of its LNG exports from that market each year, subject to certain adjustments. However, the Energy Minister may, by legislative instrument, reduce that percentage if the Energy Minister is satisfied that demand and supply conditions in the relevant market are appropriate to make that determination. Among other things, the Energy Minister must first consult the Industry Minister and take advice from the AER.
    • The Levy Bill imposes a cost-recovery levy on export licences granted under the Principal Bill.
    • The Amendments Bill amends the Competition and Consumer Act 2010 and the Competition and Consumer (Gas Market Code) Regulations 2023 (Gas Market Code) to give operational effect to the Domestic Gas Reservation Scheme, and the Customs (Prohibited Exports) Regulations 1958 to repeal the existing export controls.

    The Domestic Gas Reservation Scheme will replace the Australian Domestic Gas Security Mechanism, which the Amendments Bill repeals from 1 January 2028 (subject to transitional arrangements for domestic shortfall quarters ending before that date).

    The Principal Bill

    The Principal Bill contains the most substantive changes, with several changes having significant commercial and legal implications for licence holders.

    Definition of "existing contract"

    The Principal Bill changes the "existing contract" definition to expressly exclude any contracts renewed or extended after 22 December 2025. The exposure drafts were silent on this issue, so this provides greater clarity to licence holders. However, it means that future renewal and extension rights will be subject to the regime. If a licence holder exercises such a right after the cut-off date, the contract will require amending for the licence holder to satisfy its DSO under the "own gas" definition.

    Renewal and extension rights are industry standard in LNG sale contracts and are typically negotiated and reflected in the contract's pricing and volume commitments. This amendment will therefore affect a large number of LNG contracts that were priced and agreed long before the regime was contemplated. In our view, the change shifts negotiating leverage to buyers at renewal, as a licence holder that needs renewed volumes to count towards its DSO may have to concede on price or other terms to secure the required amendments. Licence holders should not wait until an option is exercised. They should map renewal and extension dates against the 1 January 2028 start date, consider whether to negotiate DSO-compliant terms before exercising those rights, and ensure that new and renewed LNG sale contracts include terms that allow the gas to count towards the DSO. Licence holders should also note that existing contracts are not automatically credited towards the DSO; recognition is available only through a DSO adjustment determination, which must be applied for before 31 December 2027.

    Definition of "own gas"

    The definition of "own gas" has been broadened to apply to any related body corporate of the licence holder (as opposed to a related body corporate controlled by the licence holder). However, its application has simultaneously been tightened. The licence holder (or its related body corporate) must have held a legal or equitable interest in the gas at all times since it was produced, rather than only at the time of production.

    Extending the definition to any related body corporate allows more flexibility in terms of group and project structuring. However, the continuous interest test introduces an additional layer of complexity.

    In practice, a licence holder risks losing the ability to count gas towards its DSO if its marketing or sale structure breaks the continuous chain of legal or equitable interest, for example, where title passes to an unrelated party before the gas is supplied domestically. Structures we expect to come under scrutiny include joint venture arrangements where participants market separately, sales through third-party aggregators or traders, and gas swap, exchange or tolling arrangements. Licence holders should review these arrangements now, as any restructuring (for example, moving title transfer points or bringing marketing entities within the corporate group) may take time and require counterparty consent before the regime starts on 1 January 2028.

    Ministerial consideration of existing domestic gas reservation arrangements

    The Principal Bill now requires the Energy Minister to consult the relevant State or Territory government about existing domestic gas reservation arrangements before decreasing the DSO percentage (a varied DSO percentage). This amendment is likely an acknowledgement of the overlap between the DSO and the domestic supply obligations under the existing Western Australian domestic gas reservation policy. While this adds a procedural safeguard, the overlap with State reservation policies a live concern, as it remains unclear how the new regime will co-exist with existing State obligations.

    For Western Australian exporters, the key question is whether gas supplied under the State policy will also count towards the DSO, or whether they face two separate obligations. Without clear alignment, there is a risk of double obligations for the same gas, which could affect project economics and investment decisions for new Western Australian (WA) developments. We expect this to be a focus of industry engagement as the rules are developed, and WA exporters should model both scenarios in their planning.

    The Levy Bill

    The Levy Bill is substantively unchanged from the exposure draft. The calculation of the levy amount therefore remains the key uncertainty for stakeholders.

    As currently drafted, the levy amount will be determined under regulations, which may prescribe different amounts or calculation methods for different classes of licence holders. Stakeholders will need to wait until those amounts and calculations are prescribed.

    The Amendments Bill

    The Amendments Bill contains a number of changes, although many are clarifying rather than substantive.

    A key amendment is an expanded role for the Energy Minister. The AER still makes determinations for gas production baselines and additional gas decisions, but the Energy Minister may now specify factors that the AER's forecasting and demand calibration methods must include, and must agree to Gas Market Code provisions made for the Domestic Gas Reservation Scheme. The Amendments Bill further provides the Energy Minister with specific powers to determine, by legislative instrument, quantities of natural gas that are "additional gas".

    The selling practice requirements in the exposure drafts are largely unchanged and will start on 1 July 2027. These include an expression of interest framework for the sale of domestic gas, and a new good faith factor of whether a licence holder "unreasonably refused" an offer.

    From 1 July 2027, the Gas Market Code will be amended to remove the $12/GJ price cap. The Gas Market Code will also set out the specific circumstances (called flexibility requirements) in which a licence holder may defer up to 10% of its DSO. Under the Principal Bill, any deferred amount must be made up within the following three regulated periods (years). The flexibility requirements are prescriptive and broadly include where a licence holder has used best endeavours to sell uncontracted regulated gas, where an unrelated buyer has a call option but does not exercise it, or where there are exceptional circumstances (that is, circumstances not reasonably foreseeable and outside the control of the licence holder or another body corporate acting on its behalf). The AER is expected to provide further detail through instruments.

    Taken together, the removal of the price cap, the expression of interest framework, the new "unreasonably refused" good faith factor and the deferral flexibility will change how domestic gas is contracted. Domestic buyers are likely to rely on the "unreasonably refused" factor in negotiations, so licence holders should document how they assess offers and why any offer is declined. The "best endeavours" deferral ground is also likely to depend on a clear record of marketing efforts. Establishing these processes before 1 July 2027 will put licence holders in a stronger position with both buyers and the AER.

    Key uncertainties in the exposure drafts largely remain, and they are compounded by the broad discretion given to the AER and the Energy Minister. In particular, it is not yet clear how the AER's forecasts of domestic demand and supply for the target aggregate supply will be calculated, as the method remains to be determined by the AER by legislative instrument. The Amendments Bill further adds a broad discretionary element by allowing the Energy Minister to specify factors that the AER's method must include. Until these instruments are made, or further Government guidance is provided, stakeholders may find it difficult to settle their future strategies and compliance approach. This uncertainty has practical consequences. Licence holders may need to decide whether to apply for a DSO adjustment determination (before 31 December 2027) before the forecasting method is finalised, and lenders and investors are likely to look for this risk to be addressed in project financing and new contracts. We recommend that licence holders engage early in consultation on the AER's method and build flexibility into new domestic and export contracts.

    What's next?

    The bills passed the House of Representatives on 29 October 2026 and were referred to the Senate Economics Legislation Committee. On 11 November 2026, the Committee recommended that the Senate pass the Principal Bill and its two companion bills without amendment. The bills now await debate and a vote in the Senate.

    Given the Committee's recommendation, we expect the bills to pass the Senate without significant amendment. The focus will then shift to the subordinate instruments, including the AER's forecasting method, the levy regulations and the Gas Market Code amendments, which will determine how the scheme operates in practice. Licence holders should use the period before 1 July 2027 to review their contracts and structures and engage in consultation on these instruments. Ashurst Perkins Coie will continue to monitor these developments and provide timely updates.

    Authors: Jessica Davies, Partner; Justin Jones, Partner; Mason Ku, Lawyer and Elizabeth Hewish, Graduate.

    The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
    Readers should take legal advice before applying it to specific issues or transactions.