The ESEM is coming
The Department of Climate Change, Energy, the Environment and Water (DCCEEW) released the draft regulatory package to establish the Electricity Service Entry Mechanism (ESEM) and the Market Making Obligation (MMO) on 14 September 2026.
The ESEM will replace the Capacity Investment Scheme for long-term investment in the energy sector.
In this update, we consider where DCCEEW and the ECMC have taken the development of the ESEM under the Draft Bill and Draft Rule.
It will have the following features:
However, key uncertainties remain, including:
The National Electricity Market wholesale market settings review (NEM Review) began in November 2024. The Final Report was published on 16 December 2025 (NEM Review Report). The Energy and Climate Change Ministerial Council (ECMC) noted the Final Report and agreed in principle to its core recommendations (Queensland reserved its position) (see our report).
The NEM Review Report made 12 recommendations for improving the national electricity market in the short, medium, and long term. A key recommendation was (in summary):
Implementation of the recommendations is being managed by DCCEEW.
In September 2026, the ECMC, excluding Queensland, agreed to release a draft regulatory package for the ESEM and the MMO for consultation (National Electricity Market Wholesale Market Settings Regulatory Reforms - Department of Climate Change, Energy, Environment and Water). The package consists of:
Consultation closes on 13 October 2026.
The ECMC will reconsider it in December 2026, with the aim of legislating in the first half of 2027.
In this update, we look at where DCCEEW and the ECMC have taken the development of the ESEM under the Draft Bill and Draft Rule.
Clause 4AA.C.6 of the Draft Rule provides for the ESEM to apply to:
Clause 4AA.C.6 of the Draft Rule also provides for sub-services – for essential services, strategic reserves, and special purpose procurements.
The NEM Review Report left open one key ESEM design element: how to establish the volume of contracts required for each ESEM service on a periodic basis.
Clause 118AAH of the Draft Bill sets out the ESEM’s purpose: to facilitate investment delivering ESEM services that promote the entry objective.
Clause 118AAI defines the entry objective as meeting the following at the lowest cost to electricity consumers:
Clauses 4AA.C.1 – 4AA.C.4 of the Draft Rule set out a two-yearly cycle involving:
Comment: The ESEM (General) Guidelines (see clause 4AA.C.36 of the Draft Rules) will set out how the anticipated entry trajectory is determined and translated into the tender plan. The ESEM Administrator will develop these guidelines, but not until 2027.
The Draft Bill (clauses 118AAL and 118AAM) establishes two entities:
Under the Draft Bill, the ESEM Administrator and the FME could be the same entity (to be determined by the ECMC).
Questions persist about the FME’s financial strength and risk appetite for recycling ESEM contracts.
The Draft Bill (clauses 118AAR to 118AAZ) and the Draft Rule (clauses 4AA.C.27 to 4AA.C.33 and 4AA.C.37) establish a cost recovery process aimed at enabling the FME to achieve an investment-grade credit rating.
The key outcomes in the process (on a region-by-region basis) are:
Because AEMO will recover ESEM costs, it may draw upon prudential and credit support arrangements of the Market Customers under the NER (including where the Market Customer has been suspended from the NEM).
The accompanying DCCEEW consultation paper says:
"The FME will have a statutory right to recover costs from Market Customers. Appropriate cost recovery arrangements (see Section 2.3.1) will support the FME to achieve an investment-grade credit-rating, giving market participants confidence in their counterparty."
Under the Draft Bill and Draft Rule, the FME will warehouse exposure from procured ESEM contracts and sell them as electricity derivatives to offset its exposures. The FME may sell products using exchanges, running auctions, or over-the-counter trading (which is expected to be its principal method).
This process will require the FME to be the enduring counterparty to both the ESEM contracts awarded to meet the anticipated entry trajectory and the offsetting trades.
A Risk Management Framework will govern these processes (see clause 118AAQ of the Draft Bill and clauses 4AA.C.21 – 4AA.C.26 of the Draft Rule). The Draft Bill and Draft Rule include the machinery for its establishment, but the broad statements do not seem to significantly restrict the types of trades and recycling by the FME.
Comment: The FME’s market-facing functions and risk appetite will remain unclear until the ESEM Administrator prepares the Risk Management Framework in 2027. This document will be key in determining the FME’s financial capacity to support ESEM contracts.
Our Energy Alert (What the ESEM Contracts could look like – have your say) considers the Electricity Contract Co-Design Working Group's consultation paper on proposed ESEM contracts.
The Draft Rule includes provisions for the Electricity Contract Co-Design Working Group’s ongoing operation (see clauses 4AA.D.1 – 4AA.D.7).
The entity (and the project, if relevant) must:
Clause 4AA.C.8 of the Draft Rule details the ESEM project criteria.
The project must be:
It must not be:
The target Commercial Operations Date must be before the relevant ESEM in-market period (which includes the period before the commencement of the ESEM contract period).
Comment: Our separate review of the draft ESEM Contracts highlighted risk mitigants, including a portfolio approach relying on backing from existing assets (consistent with the ESEM’s purpose). This proposed ESEM project criteria seems to limit the possibility of portfolio based bids – clarification on this approach would be very beneficial.
Clause 4AA.C.18 of the Draft Rule provides important guidance on this contract’s form. Parties must enter into it at the time of the ESEM contract.
It must:
Clause 118AAZF of the Draft Bill excludes the common law doctrine of penalties for damages payable under an ESEM contract or ESEM-related contract for missing a project milestone or other deadline.
Comment: Projects awarded contracts under the Capacity Investment Scheme have often failed to proceed. The bonding requirement on the Notice-to-Proceed Date, combined with the statutory exclusion of the common law doctrine of penalties, seems intended to address this issue.
Under clause 118AAX of the Draft Bill, a Market Customer can receive partial ESEM cost relief where it has supported or underwritten the construction or development of a project or facility that:
Clause 4AA.C.34 of the Draft Rule includes the machinery to give effect to this concept.
Comment: These provisions attempt to provide complementary relief for Market Customers required to establish new generation or energy storage systems to support large loads. They clearly respond to recent Federal policies on data centre build-out.
The DCCEEW consultation paper recognises this is an early draft of the cost relief content – there are a number of features that need refinement, so watch this space.
The Draft Bill allows non-inaugural participating jurisdictions to opt in.
Comment: Queensland has not agreed to the ESEM. However, the ESEM can commence without Queensland, and Queensland can join later.
The ESEM will fundamentally reshape how new generation and storage projects are sponsored by government in the NEM, replacing the Capacity Investment Scheme with a more structured regulatory framework. Key considerations by stakeholder type:
The DCCEEW consultation on the Draft Bill and Draft Rule closes on 13 October 2026. Key milestones:
Authors: Dale Gill, Partner; Paul Newman, Consultant and Isabelle Jardine, Graduate.
Data centre demand is forecast to surge from around 3% to approximately 13% of electricity supplied through the grid by 2035–36. This would fundamentally reverse a long-term trend of declining demand and rival the load of the largest industrial consumers in the NEM.
In this episode, Dale Gill and Paul Newman examine the two-pronged regulatory response emerging at the Commonwealth and State level. They consider the AEMC's recommendations on renewable offset and firming mandates, as well as NSW's requirement that data centres source 40% of their electricity from wind and contract for firming capacity. They also explore the competitive tension these massive new loads will create, alongside the retirement of coal-fired generation, for those developing and contracting energy projects.
The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
Readers should take legal advice before applying it to specific issues or transactions.