Legal development

FERC Meeting Agenda Summaries for October 2026

    Below are brief summaries of the agenda items for the Federal Energy Regulatory Commission's (FERC or the Commission) open meeting to be held on October 15, at 10:00 a.m. ET.

    The summaries below are based on publicly available information in the dockets listed on the FERC agenda at the time of publication. For ease of reference, a link to each lead docket on the meeting agenda has been included. The Commission may decide to remove any items from the meeting agenda at any time.

    Item No. Docket No. Company
    Administrative
    A -1  AD27-1-000

    Agency Administrative Matters

    A- 2 AD26-2-000

    Customer Matters, Reliability, Security, and Market Operations

    Electric
    E - 1 EL25-92-001

    McKenzie Electric Cooperative, Inc. v. Basin Electric Power Cooperative

    On June 22, 2026, McKenzie Electric Cooperative, Inc. (McKenzie) filed a request for rehearing of FERC's May 2026 order denying McKenzie's complaint. The underlying complaint alleged that Basin Electric Power Cooperative (Basin) pursued a nominal Rural Utilities Service (RUS) loan to avoid FERC jurisdiction. McKenzie argues that rehearing is warranted because FERC failed to provide "any reasoned analysis" of whether Basin's purposeful evasion of federal jurisdiction was compatible with the public interest, as required by FPA section 204.

    Two intervenors—Sierra Club and Tri-State Generation and Transmission Association, Inc. —also filed requests for rehearing. They make similar claims about the May 2026 order.

    Agenda item E-1 may be an order on the rehearing requests.

    E - 2 RR26-3-000

    North American Electric Reliability Corporation

    On August 24, 2026, the North American Electric Reliability Corporation (NERC) filed a request with FERC for acceptance and approval of (1) its 2027 proposed business plan and budget; (2) the proposed business plans and budgets for the regional entities for 2027; and (3) the proposed assessments to fund the budgets.   

    Agenda item E-2 may be an order on NERC's request.

    E - 3

    EL26-84-000 

    QF26-1177-001

     

    IGS CTS, LLC

    On June 18, 2026, IGS CTS, LLC (IGS CTS) filed a petition for a declaratory order asking FERC to grant a partial, limited waiver of the certification requirement in 18 C.F.R. § 292.203(a)(3). The waiver that IGS CTS requests would allow its solar photovoltaic generating facility (the Facility) to be deemed a qualifying facility, eligible for the regulatory exemptions in 18 C.F.R. §§ 292.601 and 292.602, for the period from December 3, 2025, through June 17, 2026. IGS CTS seeks the waiver because it inadvertently failed to timely file a required self-certification form (Form 556) for the Facility.

    Agenda item E-3 may be an order on IGS CTS's petition. 

    E - 4 EC26-110-000

    FirstLight Power Management LLC, FirstLight CT, Housatonic LLC, FirstLight MA Hydro LLC, Northfield, Mountain LLC, and Hull Street Energy, LLC 

    On June 15, 2026, FirstLight Power Management LLC, FirstLight CT Housatonic LLC, FirstLight MA Hydro LLC, Northfield Mountain LLC (collectively, Project Companies), and Hull Street Energy, LLC (HSE) filed a joint application for authorization under Section 203 of the Federal Power Act requesting Commission authorization for the proposed acquisition by HSE FirstLight, LLC (Buyer) of 100% of the ownership interests in PSP FL USA LLC, which indirectly owns 100% of the ownership interests in the Project Companies. On July 20, 2026, the Project Companies submitted supplemental analysis to reflect that Buyer will be associated with additional generation capacity in the relevant market, ISO-NE.

    Agenda item E-4 may be an order on the joint application.

    E - 5 ER24-2045-005

    PJM Interconnection, L.L.C.

    On June 15, 2026, PJM Interconnection, L.L.C. (PJM) submitted a compliance filing in accordance with the Order on Compliance issued by the Commission in April 2026 in the “Improvement to Generator Interconnection Procedure and Agreements” proceeding. The compliance filing revises PJM’s Open Access Transmission Tariff (OATT) consistent with the Order, including seeking Commission approval of independent entity variations from the relevant pro forma agreements.

    Agenda item E-5 may be an order on the compliance filing.

    E - 6

    ER26-2932-000

    TS26-5-000

     

    Mammoth Central LLC

    On June 23, 2026, Mammoth Central LLC (Mammoth Central) requested temporary waivers of FERC’s Open Access Requirements for interconnection facilities for an alternating-current solar photovoltaic-powered electric generating facility under development in Pulaski County, Indiana. Mammoth Central exercised an option to build the Transmission Owner Interconnection Facilities and Stand Alone Network Upgrades (collectively, the TOIF) for the facility and will transfer operational control of the TOIF to AEP Indiana Michigan Transmission Company, Inc. (AEP) prior to energization of the TOIF. On September 11, 2026, Mammoth Central filed a supplement to its request for temporary waivers at the request of FERC staff, providing a more detailed description of the TOIF it will transfer to AEP and the Customer Interconnection Facilities (CIF) that it will continue to own after the transfer.

    Agenda item E-6 may be an order on Mammoth Central’s request.

    E - 7

    ER26-2949-000

    TS26-6-000

     

    Mammoth South LLC

    On June 23, 2026, Mammoth South LLC (Mammoth South) requested temporary waivers of FERC’s Open Access Requirements for interconnection facilities for an alternating-current solar photovoltaic-powered electric generating facility under development in Pulaski County, Indiana. Mammoth South exercised an option to build the Transmission Owner Interconnection Facilities and Stand Alone Network Upgrades (collectively, the TOIF) for the facility and will transfer operational control of the TOIF to AEP Indiana Michigan Transmission Company, Inc. (AEP) prior to energization of the TOIF. On September 11, 2026, Mammoth South filed a supplement to its request for temporary waivers at the request of FERC staff, providing a more detailed description of the TOIF it will transfer to AEP and the Customer Interconnection Facilities (CIF) that it will continue to own after the transfer.

    Agenda item E-7 may be an order on Mammoth South’s request.

    E - 8 ER26-3431-000

    Lost Island Wind Energy, LLC 

    Lost Island Wind Energy, LLC (Lost Island) is developing the Lost Island Wind Project, a utility-scale wind generation facility located in Palo Alto County in northwestern Iowa. On July 31, 2026, Lost Island submitted a petition requesting a prospective, limited waiver of Article 2.3.1 of the Generator Interconnection Agreement (the GIA), and Section 4.4.4 of Attachment X to the Midcontinent Independent System Operator, Inc. (MISO) Open Access Transmission Tariff (the Tariff). In its petition, Lost Island seeks to extend the Project’s COD from December 14, 2028, to December 14, 2030, because litigation over the Project’s site permit, pending before the Iowa Supreme Court, has created uncertainty that has significantly disrupted the Project’s development, making compliance with the current COD as set forth in the GIA impossible to achieve. 

    Agenda item E-8 may be an order regarding Long Island’s petition for a requested waiver and COD extension.  

    E - 9 ER26-3333-000  

    Deseret Generation & Transmission Co-operative, Inc.

    On July 30, 2026, Deseret Generation & Transmission Co-operative, Inc. (Deseret) filed a notice of change in status, as well as tariff revisions to reflect its participation in the Southwest Power Pool Integrated Marketplace as well as the California Independent System Operator Extended Day Ahead Market. 

    Agenda item E-9 may be an order regarding Deseret’s filing.

    E - 10

    ER23-2595-001

    ER23-2595-000

    EL23-98-000

     

    Stony Creek Wind Farm, LLC 

    On August 9, 2023, Stony Creek Wind Farm, LLC (Stony Creek) filed an informational filing relating to its rate schedule for Reactive Supply and Voltage Control from Generation or Other Sources Service (Rate Schedule). The filing concerned a planned upstream change in control of the Stony Creek generating facility. On September 18, 2023, FERC accepted Stony Creek’s filing and instituted a Section 206 proceeding regarding the continued justness and reasonableness of Stony Creek’s Rate Schedule. The parties reached a contested settlement of the proceeding, which was submitted to FERC on April 19, 2024.

    Agenda item E-10 may be an order on the proposed contested settlement.

    E - 11

    EL26-80-000

    QF14-355-003  

     

    Conyers Renewable Power, LLC

    On June 16, 2026, Conyers Renewable Power, LLC (Conyers) submitted a petition for a declaratory order requesting a partial waiver from the filing requirement of Section 292.203(a)(3) of the Commission’s regulations for a qualifying small power production facility to correct an administrative oversight resulting in a failure to recertify the qualifying facility status of a 3.2 MW landfill gas generation facility after upstream ownership of Conyers changed in 2020. Conyers submitted a report of refunds to the buyer of the project’s output resulting from the absence of a properly filed recertification of QF status.

    Agenda item E-11 may be an order on Conyers’s petition.

    Gas
    G - 1 RM93-11-004

    Revisions to Oil Pipeline Regulations Pursuant to the Energy Policy Act of 1992 

    On December 22, 2025, Kinder Morgan, Inc. (KMI) requested limited clarification or, in the alternative, rehearing of the Commission’s November 20, 2025, order (the Remedies Order) granting remedial relief to certain liquids pipelines for a period ranging from March 2022 into September 2024 (the Locked-In Period) in order to place those pipelines in the position they would have been in absence of the issuance of a now-vacated earlier order. KMI’s filing noted that KMI fully supports the remedial relief granted in the Remedies Order, but it sought clarification that the Commission did not intend to limit the circumstances under which remedial relief is available to pipelines to just those instances where pipelines were charging the maximum rates permitted under the now-vacated earlier order. In the alternative, KMI sought rehearing of the Remedies Order to the extent it prohibits pipelines that charged rates below certain Maximum Rehearing Index Rates but that were still impacted by the now-vacated earlier order from obtaining the same remedial relief as that afforded to pipelines that charged the Maximum Rehearing Index Rates during the Locked-In Period. 

    On the same day, Energy Transfer LP (Energy Transfer) requested clarification of the Remedies Order that the recouped assessments for “amounts that would have been chargeable” during the Locked-In Period include interest on the calculated amounts. 

    Agenda Item E-11 may be a further order on RMI’s and Energy Transfer’s requests for rehearing and clarification.

    G - 2 RM20-14-005

    Five-Year Review of the Oil Pipeline Index 

    The requests for clarification or rehearing, filed in Docket No. RM93-11-004 were also filed in Docket No. RM20-14-005. 

    Agenda item G-2 may be an order on these requests.

    Certificates
    C - 1 RM26-2-001

    Authorizations for Certain Activities at Liquefied Natural Gas Plants

    On November 20, 2025, the Commission issued a notice of inquiry seeking information and stakeholder perspectives to help the Commission explore whether, and if so how, to establish procedures for authorizing activities at liquefied natural gas (LNG) plants without the need for case-specific authorization applications and orders under Sections 3 or 7 of the Natural Gas Act (NGA). Between January 16, 2026, and January 27, 2026, several entities submitted comments for the Commission’s consideration. 

    Agenda item C-1 may be a further issuance relating to the Commission’s notice of inquiry.

    C - 2 PL26-3-000

    Environmental Review of Natural Gas Act Applications

    PL26-3-000 is a brand new policy docket concerning the Environmental Review of Natural Gas Act Applications. 

    Agenda item C-2 may be an initial issuance relating to the Commission’s environmental review.

    C - 3 CP26-11-000

    Columbia Gulf Transmission, LLC

    On October 15, 2025, Columbia Gulf Transmission, LLC submitted an Abbreviated Application for Certificate of Public Convenience and Necessity pursuant to Section 7(c) of the Natural Gas Act to construct and operate certain natural gas pipeline facilities through its Pulaski Project, which would service new and existing generation resources at the John S. Cooper Power Station and supply 253 million standard cubic feet per day of natural gas transportation. On January 7, 2026, the Commission issued Notice Of Schedule for the preparation of an Environmental Assessment for the project. 

    Agenda item C-3 may be related to the environmental review and/or the CPCN for the Pulaski Project.

    C - 4

    CP26-537-000

    CP17-118-000

    Louisiana LNG Infrastructure LLC

    Driftwood Pipeline LLC

    On June 1, 2026, Louisiana LNG Infrastructure LLC (Louisiana LNG) submitted an application for limited amendment to authorization granted under Section 3 of the Natural Gas Act and request for expedited action. The authorization was granted in 2019 to Louisiana LNG’s predecessor, Driftwood LNG LLC (Driftwood), in Docket No. CP17-117-000. The requested amendment would incorporate an interconnect and receipt meter station (the KMLP Interconnect) that would interconnect the Louisiana LNG facility with the Kinder Morgan Louisiana Pipeline LLC (KMLP) interstate natural gas pipeline system, allowing Louisiana LNG to serve as a significant source of natural gas supply for the Project quicker than is available from other supply sources. Simultaneously, Driftwood Pipeline LLC requested to vacate this same facility from its facilities authorized under Section 7(c) of the Natural Gas Act (Docket No. CP17-118-000). On June 30, 2026, the Commission issued an Environmental Assessment Report for Louisiana LNG and Driftwood’s application.

    Agenda item C-4 may be an order on this application.

     

    The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
    Readers should take legal advice before applying it to specific issues or transactions.