APAC's energy transition in 2027: the race to connect, contract and finance clean energy
In 2027, the defining challenge for Asia-Pacific's (APAC) energy transition will be building the systems that make clean energy investable and usable at scale. The technologies are established. The harder questions are whether grids can connect new generation and major energy users, whether electricity markets reward flexibility, whether regional power trading can develop beyond physical interconnection, and whether projects can offer the contractual certainty that long-term capital requires.
These pressures are converging. Electrification, data centres, artificial intelligence (AI) and industrial expansion are reshaping electricity demand, while ageing generation assets retire and governments seek to balance decarbonisation with energy security, affordability and economic competitiveness.
Energy security has also returned to the centre of policy and investment decisions. The conflict in the Middle East has tightened liquefied natural gas markets, and higher and more volatile prices have pushed some fuel switching back towards coal in price-sensitive APAC markets. Gas is likely to retain an important, but increasingly uncertain, role as a source of firming and a transition fuel. Wood Mackenzie expects less than a third of planned Southeast Asian gas-fired capacity to be delivered by 2030, which raises questions about how firm capacity will be secured if that pipeline does not materialise. Over the longer term, nuclear power is re-emerging as a potential source of firm, low-emissions generation, with renewed activity in Vietnam, Indonesia and the Philippines, although new capacity is unlikely to contribute before the 2030s.
Some of these themes were explored in the first edition of this series. This article focuses on what is new: against that backdrop, five key developments are likely to shape APAC's energy-transition investment landscape in 2027.
The scale of the infrastructure challenge is already apparent. The International Energy Agency's (IEA) Southeast Asia Energy Outlook 2026 estimates that transmission and distribution networks in Southeast Asia will need to more than double in length by 2050 to accommodate rising demand and increasingly variable supply. Under the region's announced pledges, investment in grids and storage would need to increase from around US$13 billion today to US$50 billion by 2050. Planned cross-border interconnections under the ASEAN Power Grid are estimated to require approximately US$27 billion of investment to 2040.
Australia faces a similar challenge. The Australian Energy Market Operator's (AEMO) 2026 Integrated System Plan identifies renewable generation connected through transmission and distribution networks, firmed by storage and backed up by gas, as the most cost-effective pathway for maintaining secure and reliable electricity supply as coal generation retires. AEMO forecasts that electricity consumption in the National Electricity Market will nearly double by 2050.
As renewable generation, storage and electricity demand expand, the availability of a suitable connection will not necessarily coincide with the location of the best renewable resources or the strongest customer demand. A project may be technically viable and commercially attractive on paper, yet remain exposed to connection delays, network augmentation costs, congestion or curtailment.
These constraints directly affect investment decisions. Connection rights and milestones may influence project valuation, debt sizing, conditions precedent and the allocation of development risk. Investors will need to assess not only whether a connection is available, but also its timing, cost, operational constraints and resilience to changing network requirements. Grid access can no longer be treated as a technical workstream resolved after the commercial terms are agreed; it must be assessed alongside land rights, planning approvals, offtake and financing from the outset.
Developers should factor network capacity and complementary infrastructure into site selection and project design. Lenders may adjust the amount and timing of debt to reflect connection uncertainty. Sponsors and contractors will need to allocate connection delays, changes in technical requirements and associated costs carefully across development agreements, engineering, procurement and construction (EPC) contracts, offtake agreements and financing documents.
The broader implication is that the value of an energy asset will depend increasingly on its place within the electricity system, not simply on its generation capacity or underlying technology.
As the share of variable renewable generation grows, so does the value of flexibility. Batteries, demand response, interconnection and flexible generation help balance supply and demand, manage congestion and maintain system security, while hybrid projects and flexible industrial loads can add further system value. The commercial challenge is turning these services into predictable, appropriately priced revenue. In 2027, the contractual structures supporting storage and other flexible assets are likely to become more sophisticated as investors and lenders manage the interaction between contracted income and exposure to volatile markets.
A battery may generate revenue through energy arbitrage, ancillary services, capacity arrangements or network services. These revenue streams can complement one another, but they also introduce different operational requirements and market risks. Changes in electricity prices, market rules, congestion, negative pricing or the availability of ancillary services can materially affect the overall revenue profile.
There is no single contracting model that will suit every project. Revenue-sharing arrangements, tolling structures, capacity contracts, availability guarantees and merchant exposure will each have a role, depending on the asset, market and the investor's risk appetite.
Recent Australian transactions illustrate the direction of travel. In 2026, we advised on a revenue-share agreement providing revenue certainty for the development of a battery in Australia, allowing the developer to retain operational control while managing market risk. Battery financings in Australia also show that lenders can assess merchant battery revenues where market exposure, technical characteristics and risk allocation are appropriately structured. The commercial architecture supporting an asset can be as important to its investment case as the technology itself.
Contractual arrangements will need to address performance degradation, availability, dispatch rights, negative prices, curtailment, changes in market design and the interaction between different revenue streams. Where an asset depends on several sources of income, parties will need to understand how those sources interact and whether one contractual commitment could constrain another.
In 2027, the ability to structure, contract and finance flexibility will become an increasingly important source of competitive advantage.
Demand is changing the energy-transition story as much as supply. Data centres, AI infrastructure, advanced manufacturing, hydrogen production and electrified industrial processes require large volumes of electricity and have demanding requirements for reliability and connection timing. As a result, generators, network operators and major customers are being drawn into closer relationships.
In 2027, large energy users are likely to shape energy infrastructure, not simply buy electricity from existing markets. Where grid capacity is constrained or connection timelines are uncertain, they may pursue long-term power purchase agreements, direct investment in generation and storage, behind-the-meter solutions or dedicated supply arrangements, depending on the market's regulatory framework and network arrangements. A creditworthy customer with a clear long-term demand profile can underpin contracted revenues and access to finance, and may act as an anchor around which new infrastructure is developed.
Governments and regulators will face related questions about how scarce network capacity should be allocated, who should bear the cost of infrastructure upgrades and how the needs of large new loads should be balanced against affordability and reliability for other users.
These questions are already moving from principle to policy. In Australia, the Australian Energy Market Commission's reforms addressing the connection and integration of data centres and other large loads are progressing. Similar questions about large-load connection, network cost allocation and dedicated supply arrangements are being considered in other APAC markets, suggesting that the frameworks governing large energy users will become clearer, and more consequential for investment decisions, during 2027.
Given the increasingly close relationship between energy and digital infrastructure, the best opportunities for investors and developers may lie in structuring integrated solutions around a customer's long-term energy requirements, not only in supplying electricity. For legal advisers, this requires a broader view of the transaction, considering electricity contracts, infrastructure access, planning approvals, construction arrangements and corporate investment structures together.
The ASEAN Power Grid reflects a shift from viewing interconnection as an infrastructure project to treating it as part of a wider market and regulatory system. Cross-border transmission can help countries share generation resources, improve resilience and make better use of renewable energy, but physical interconnection alone does not create a functioning regional market. The ASEAN Centre for Energy's 2026 work on multilateral power trading identifies market rules, governance structures and institutional coordination as necessary components, alongside greater alignment of technical standards and regulatory frameworks.
In 2027, progress towards regional power integration is likely to increase the importance of the commercial and legal arrangements governing how electricity is traded across borders. These arrangements raise questions that extend well beyond the construction and operation of an interconnector. Who has rights to transmission capacity? How are congestion and curtailment allocated? Which jurisdiction's rules apply to a cross-border transaction? How are system-security obligations coordinated? What happens when a participating country's regulatory settings change? How are costs and revenues allocated, and how are disputes resolved?
The answers will influence the bankability of regional infrastructure. Investors need sufficient clarity about the rights and obligations associated with an asset, the basis on which revenues will be earned and the extent to which those arrangements can withstand changes in regulation or government policy.
The IEA's 2026 analysis of financing the ASEAN Power Grid also highlights the need for financing approaches and business models to keep pace with the scale and complexity of the interconnection pipeline. Where projects involve several governments, utilities, regulators and financiers, interests may diverge and the allocation of construction, operating, market and political risk may become more complex. Progress will depend on workable trading arrangements, coordinated system operation and sufficient regulatory certainty to support long-term investment.
These issues are especially relevant to ASEAN and should not be assumed to apply uniformly across APAC, where markets, institutions and cross-border arrangements differ considerably. For developers and investors, regional energy transactions will require closer integration of project structuring, regulatory analysis, government arrangements and financing; managing differences between national frameworks may become as important as delivering the infrastructure itself.
Capital will remain essential to APAC's energy transition, but the availability of funding does not automatically translate into investable projects. The IEA estimates that Southeast Asia's energy investment exceeded US$100 billion in 2025, representing around 3% of global energy investment. It also notes that the cost of capital in much of Southeast Asia can be around twice that of advanced economies and China, materially affecting the economics of capital-intensive clean energy projects.
These conditions make bankability critical: where financing costs are high, uncertainty around grid access, construction, revenue or regulation can determine whether a project proceeds and on what terms.
In 2027, investors and lenders are likely to differentiate more sharply between projects based on risk-adjusted returns and the quality of their contractual, regulatory and infrastructure arrangements. This places greater emphasis on early-stage due diligence: whether land rights and permits are robust, the grid connection is sufficiently certain, revenue assumptions are realistic and the project can withstand changes in market design or government policy.
The durability of the regulatory framework will be particularly important for assets with investment horizons of 20 or 30 years. Governments across APAC are balancing decarbonisation with energy security, affordability, local manufacturing, critical minerals development and investment attraction. Those objectives can conflict, creating uncertainty for projects that depend on long-term regulatory or government support.
Not all such risks can be transferred contractually. Change-in-law provisions, termination rights, compensation mechanisms and government support arrangements can help allocate or mitigate exposure, but their effectiveness will depend on the applicable legal framework and the creditworthiness of the relevant counterparties and the enforceability of their commitments.
The cost and availability of capital will also shape investment structures. Depending on the market and project, bankability may be supported by long-term offtake, credit enhancement, guarantees, concessional financing, structured equity (which is increasingly common) or a carefully structured allocation of construction and operating risks. The objective is not to eliminate uncertainty, but to ensure the risks each party retains are understood, appropriately priced and manageable.
These considerations are also likely to shape M&A activity. As energy-transition markets mature, investors may increasingly seek platforms and portfolios rather than individual projects. Renewable generation, storage, transmission infrastructure, energy retailing, trading capabilities and distributed energy resources can offer complementary sources of value and opportunities to diversify exposure.
Ashurst Perkins Coie's 2026 M&A analysis identified continued capital flows into renewables, storage, transmission and transition-related infrastructure, alongside growing investor interest in critical minerals and other assets supporting the energy transition. This points towards a more integrated investment thesis: the value may lie not only in individual generation assets, but also in the infrastructure, customers, market access and commercial capabilities that allow those assets to operate successfully.
For investors, the challenge will be to distinguish between projects that offer attractive headline returns and those that can deliver sustainable risk-adjusted returns over their operating lives. For developers, it will be increasingly important to establish bankability early, rather than assume that capital will be available once the asset is built.
APAC's energy transition in 2027 will be shaped less by technology than by the systems, contracts and capital that surround it. Grid access, flexibility, large energy users, regional integration and selective capital are closely linked: each turns on how risk is identified, allocated and financed. The projects and platforms that succeed will be those that address connection, revenue, regulatory and financing questions from the outset, rather than treating them as matters to resolve once the asset is built.
Authors: Anita Choi, Partner, and Nigel Deed, Partner.