Data Centres in Italy: the new Regional law of Lombardy
On 20 June 2026, Lombardy Regional Law No. 11 of 3 June 2026, entitled “Provisions on the siting of data centres” (the “Law”), entered into force1.
The Lombardy Region recently enacted a Law pursuing the following objectives:
The new Regional Law may serve as a reference model for other Italian Regions implementing the national single procedure under Art. 8 of the Energy Bills Decree, helping to mitigate regulatory fragmentation pending comprehensive national sectoral legislation.
The main provisions of the Law are summarised below by way of executive summary, and then analysed in detail in the subsequent sections of this alert:
Siting priorities and incentives: the Law establishes siting priorities favouring brownfield and disused areas, mandates carbon-neutral energy sources, thermal energy reuse and water-efficient cooling, and provides cumulative incentive measures (reduced procedural timeframes, simplified protocols, priority access to regional funding, reduction of the construction contribution by 10-30%, and reduction of parking areas by 50-75%). An innovative urban planning classification based on connection capacity (> 5 MW: productive designation; ≤ 5 MW: compatible with productive, tertiary and office designations) enables “edge” data centres in consolidated urban areas. Significant disincentives apply to siting on agricultural land (construction contribution increased by 100-200%).
Authorisation procedures: a dedicated Regional Data Centre Office acts as single point of contact. The Region is the competent authority for the Integrated Environmental Authorisation (AIA) for data centres between 50 MW and 300 MW2 within the single procedure under DL 21/2026. A mandatory energy report covering on-site renewable maximisation, supply justifications, predictive KPIs and a heat-recovery feasibility study is required. A multi-agency task force will issue technical-administrative guidelines.
Supra-municipal relevance: projects with connection capacity > 10 MW are classified as being of supra-municipal relevance and require a consultative concertation conference, leading to a territorial agreement with equalisation and compensatory measures. The conference is convened by the Region for projects > 50 MW or inter-provincial projects. A photovoltaic deduction mechanism allows on-site renewable capacity to reduce the applicable thresholds.
Brownfield mapping: municipalities must identify and update disused, contaminated, degraded, unused or underused areas within 365 days; data must be published via the geoportal within 60 days. Municipal non-compliance does not preclude applications for data centre siting.
Monitoring: a Permanent Steering Committee performs advisory and impact-assessment functions; interoperability with the European database under Regulation 2024/1364 is ensured.
Transitional regime: the new procedures apply from the publication of technical-administrative guidelines (expected within 60 days of entry into force). Pending AIA procedures are concluded by the Metropolitan City/Province. Key Regional Government resolutions must be adopted within 30-60 days.
Operational guidance: the power threshold system (5 MW / 10 MW / 50 MW) is determinative for identifying the applicable urban planning and authorisation regime; the energy report is the key compliance document; the photovoltaic deduction mechanism constitutes a structural incentive for on-site renewable integration; early coordination with the grid operator (TSO/DSO) is recommended.
Article 2 of the Law establishes the siting priorities and energy-environmental conditions for data centre siting:
The technical criteria, parameters and detailed thresholds shall be defined by resolution of the Regional Government within 60 days of the entry into force of the Law, with reference to the energy and sustainability KPIs of EU Regulation 2024/1364. Furthermore, Article 3 provides for potentially cumulative incentive measures for projects complying with the energy-environmental priorities set out above:
Such measures are defined in compliance with environmental, urban planning and building regulations, as well as the principles of competition, proportionality, transparency and non-discrimination. Municipalities may provide, within their urban planning regulations, additional incentive measures (Art. 3, paragraph 3).
In addition, with respect to urban planning aspects which are relevant for siting purposes, Article 5 introduces an innovative urban planning classification system based on connection capacity:
This is a significant practical innovation that enables the siting of “edge” data centres in consolidated urban areas.
In addition, the following incentive/disincentive mechanisms should be taken into account.
Siting on brownfield areas: compensatory measures may be reduced based on the economic-financial assessment of remediation costs incurred.
Siting on agricultural land (non-priority areas): the construction contribution is increased by 100% (by 200% if in areas falling within the perimeter of protected areas under L.R. 86/1983). The proceeds are earmarked for ecological, environmental, energy and urban/territorial redevelopment compensatory measures. Such measures may also be carried out by the interested operator, by agreement with the municipality, in compliance with the prescriptions issued as an outcome of environmental assessments, where applicable (Art. 5, paragraph 4).
Article 4 regulates the authorisation procedures with the following main provisions:
Article 5, paragraph 7, provides that:
The connection capacity thresholds referred to in paragraph 7 are decreased by the total nominal capacity of photovoltaic plants installed on rooftops or on the ground within the project area, provided they fall within the priority areas under Art. 2, paragraph 1, letter a). The practical effect is to allow the project to remain below the supra-municipal relevance threshold (and the consequent concertation conference), benefiting from a more streamlined authorisation process. This constitutes a structural incentive for the integration of on-site renewable generation (Art. 5, paragraph 12).
Article 6 regulates the mapping of disused and underused areas:
The Law also establishes a monitoring system (Arts. 7–8), centred on a Permanent Steering Committee with advisory and impact-assessment functions, and on interoperability with the European database under Regulation 2024/1364.
Article 9 provides for the following transitional provisions:
Deadlines for Regional Government Resolutions (DGR) and their content:
The Law represents a significant step in the regulation of the data centre sector in Italy, positioning itself as the first regional model for the implementation of the national framework introduced by the Energy Bills Decree.
The following operational guidance is noted:
Other key contact: Gianluca Di Stefano, Senior Associate.
This is the first regional law in Italy specifically dedicated to the regulation of data centre siting. The Law fits within the national regulatory framework outlined by Article 8 of Decree-Law No. 21 of 20 February 2026 (the so-called “Energy Bills Decree” – Decreto Bollette), converted with amendments by Law No. 49 of 10 April 2026, which introduced the single authorisation procedure for data centres at the state level. The regional legislation is also in continuity with the principles and content of Bill No. 1821 (“DDL Data Centre”), which, once definitively approved, would grant the Government delegation for the organisation, construction, development and enhancement of data processing centres.
As determined by the national framework (Art. 7 (4-ter) of Legislative Decree 152/2006, as referenced by Art. 4(1) of the Law).
The implementation plan or building permit application for the construction or expansion of a data centre equipped with emergency generators must indicate the nominal thermal capacity parameter (MW) of the generators, with an indicative value for the purposes of coordination with EIA procedures and EIA screening. This value constitutes an initial reference for implementation planning purposes, without prejudice to the precise definition at the conclusion of the single authorisation procedure under Art. 8 of DL 21/2026 (Art. 5, paragraph 5). The implementation plan or application must also indicate the requested connection capacity parameter (Art. 5, paragraph 6).
The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
Readers should take legal advice before applying it to specific issues or transactions.