Natural Gas and Coal-Fired Plants To Halt Retirement Under Trump Executive Order
Last week, U.S. Secretary of Energy Chris Wright (Secretary) issued two orders under the Federal Power Act (FPA) Section 202(c), determining that emergencies exist in the grids operated by PJM Interconnection (PJM) and the Midcontinent Independent System Operator (MISO). The Secretary’s orders, No. 202-25-3 (PJM Order) and No. 202-25-4 (MISO Order), require the continued operation of a natural gas plant in PJM and a coal-fired plant in MISO that were otherwise slated for retirement.
These orders come on the heels of President Trump’s April 9, 2025, executive order, “Strengthening the Reliability and Security of the United States Electric Grid” (EO), which directed the Secretary to address what it identified as reliability risks from “an unprecedented surge in electricity demand.” The EO is targeted at ensuring that the grid uses all available power generation, including “redundant fuel supplies that are capable of extended operations.”
Both the PJM Order[3] and the MISO Order[4] determined that an emergency existed in each grid due to “a shortage of facilities for the generation of electric energy.”[5] In addition to discussing the general trend of retirement of certain generating assets in each grid, the PJM Order and MISO Order both identify specific generating units slated for retirement that the relative grid operator and owner must allow to continue to operate.[6]
The PJM Order noted the planned retirement of Constellation Energy’s Eddystone Generation Station Units 3 and 4 (Eddystone Units), PJM’s indication of possible reserve shortfalls, PJM’s attempts to address near-term adequacy concerns through tariff revisions, and other reports from PJM concerning reliability risks.[7] For example, the PJM Order notes PJM’s forecasts of high summer peak demand and a report from PJM discussing “increasing reliability risks during the transition, due to a potential timing mismatch between resource retirements, load growth and the pace of new generation entry[.]”[8] According to the PJM Order, the U.S. Department of Energy's (DOE) determination of an emergency was based on, among other things:
The PJM Order:
The PJM Order expires on August 28, 2025.[13]
The MISO Order noted potential tight reserve margins and reserve shortfalls due in part to the retirement of certain coal-fired facilities and nuclear power plants in Michigan.[14] Specifically, the MISO Order notes that a coal-fired power plant (the Plant) in Michigan, was to cease operation on May 31, 2025.[15] According to the MISO Order, DOE’s determination of an emergency was “based on the insufficiency of dispatchable capacity and anticipated demand during the summer months, and the potential loss of power to homes and local businesses in the areas that may be affected by curtailments or outages, presenting a risk to public health and safety.”[16] The MISO Order also noted an assessment from the North American Electric Reliability Corporation (NERC) indicating an elevated risk of MISO operating reserve shortfalls based on demand forecasts and resource data.[17]
The MISO Order did not touch on whether the DOE would evaluate the Plant in its uniform methodology. Like the PJM Order, however, the MISO Order required that MISO and the utility that owns the Plant “take all measures necessary to ensure that the Plant is available to operate” while minimizing environmental impacts and costs to ratepayers.[18] Also like the PJM Order, the MISO Order requires MISO to provide daily reporting, requires the utility and MISO to file with FERC any necessary tariff revisions or waivers to effectuate the MISO Orders, and notes that rate recovery is available.[19]
The MISO Order expires on August 21, 2025.[20]
The Secretary may issue further orders in the coming weeks pursuant to the EO. The EO also requires the DOE to publish its methodology to identify current and anticipated reserve margins for all regions of the bulk power system regulated by FERC by July 7, 2025.[21]
Endnotes
[2] 16 U.S.C. § 824a(c)(4)(A).
[3] Secretary of Energy Order No. 202-25-3 (May 23, 2025).
[4] Secretary of Energy Order No. 202-25-4 (May 30, 2025).
[5] PJM Order, at 1; MISO Order, at 1.
[8] PJM Order, at 1 (citing PJM, Energy Transition in PJM: Resource Retirements, Replacements & Risks, at 1 (Feb. 24, 2023).
The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
Readers should take legal advice before applying it to specific issues or transactions.
Editorial Disclaimer
Originally published before the Ashurst Perkins Coie combination. See disclaimer.